121382RESERVE NOTICE02/12/2024 04:16:59 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 02/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121359 has been updated at 1145 hrs to the following:

[1.] From 1730 hrs 02/12/2024 to 1900 hrs 02/12/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1165 MW.

Manager NEM Real Time Operations
     
121381RECLASSIFY CONTINGENCY02/12/2024 03:22:41 PM

Reclassification of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line

Duration: 02/12/2024 15:22 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
121375SETTLEMENTS RESIDUE02/12/2024 01:30:29 PM

[EventId:202412021330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 02 December 2024 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 2 December 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 2 December 2024.

Refer to market notice: 121358

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 2 December 2024.

This is an AEMO autogenerated Market Notice.
     
121374RECLASSIFY CONTINGENCY02/12/2024 01:27:11 PM

Reclassification of a Non-Credible Contingency Event: Guybal Munjan - Chalumbin 857 275kV line line and Guybal Munjan - Chalumbin 858 275kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Guybal Munjan - Chalumbin 857 275kV line and Guybal Munjan - Chalumbin 858 275kV line

Duration: 02/12/2024 13:27 until further notice

Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
121373PRICES UNCHANGED02/12/2024 12:56:56 PM

[EventId:202412021230_confirmed] Prices for interval 02-Dec-2024 12:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1250 hrs on 2 December 2024

PRICES ARE NOW CONFIRMED for trading interval 02-Dec-2024 12:30.

In accordance with Market Notice 121361 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121372PRICES UNCHANGED02/12/2024 12:55:43 PM

[EventId:202412021250_confirmed] Prices for interval 02-Dec-2024 12:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1250 hrs on 2 December 2024

PRICES ARE NOW CONFIRMED for trading interval 02-Dec-2024 12:50.

In accordance with Market Notice 121365 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121371PRICES UNCHANGED02/12/2024 12:54:32 PM

[EventId:202412021245_confirmed] Prices for interval 02-Dec-2024 12:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1250 hrs on 2 December 2024

PRICES ARE NOW CONFIRMED for trading interval 02-Dec-2024 12:45.

In accordance with Market Notice 121364 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121370PRICES UNCHANGED02/12/2024 12:52:53 PM

[EventId:202412021240_confirmed] Prices for interval 02-Dec-2024 12:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1250 hrs on 2 December 2024

PRICES ARE NOW CONFIRMED for trading interval 02-Dec-2024 12:40.

In accordance with Market Notice 121363 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121369PRICES UNCHANGED02/12/2024 12:51:43 PM

[EventId:202412021235_confirmed] Prices for interval 02-Dec-2024 12:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1250 hrs on 2 December 2024

PRICES ARE NOW CONFIRMED for trading interval 02-Dec-2024 12:35.

In accordance with Market Notice 121362 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     