115778INTER-REGIONAL TRANSFER25/03/2024 09:43:59 AM

Inter-regional transfer limit variation - SA region - 25/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - SA region - 25/03/2024

Refer market notice: 115777

At 0810 hrs 25/03/2024 there was an unplanned outage of elements:

Davenport - Brinkworth 275 kV line
Brinkworth No 3 275/132 kV transformer
Brinkworth - Templers West 275 kV line

Constraint set(s) invoked: S-X_DVBR+BRTW+TWPA


This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S_MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115775INTER-REGIONAL TRANSFER25/03/2024 06:49:58 AM

Inter-regional transfer limit variation - Armidale - Uralla 8U 330 kV line - NSW region - 25/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale - Uralla 8U 330 kV line - NSW region - 25/03/2024

A planned outage of Armidale - Uralla 8U 330 kV line in the NSW region was scheduled from 0500 hrs 25/03/2024 to 1500 hrs 25/03/2024.

The outage has been returned to service at 0645 hrs 25/03/2024.

Constraint set(s) revoked:
N-ARUL_8U
N-TW_SVC
N-X_8U+DM+TW_SVC
N-MORBOR

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1


Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115772INTER-REGIONAL TRANSFER24/03/2024 04:47:46 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 3 cable of Directlink.

The following constraint set was invoked at 1640 hrs 24/03/2024

N-MBTE_1

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
115756PRICES SUBJECT TO REVIEW24/03/2024 12:15:24 PM

[EventId:202403241220_review] Prices for interval 24-Mar-2024 12:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1215 hrs on 24 March 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Mar-2024 12:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
115755PRICES SUBJECT TO REVIEW24/03/2024 12:10:11 PM

[EventId:202403241215_review] Prices for interval 24-Mar-2024 12:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1210 hrs on 24 March 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Mar-2024 12:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
115754PRICES SUBJECT TO REVIEW24/03/2024 12:05:21 PM

[EventId:202403241210_review] Prices for interval 24-Mar-2024 12:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1205 hrs on 24 March 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Mar-2024 12:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
115753PRICES SUBJECT TO REVIEW24/03/2024 12:00:20 PM

[EventId:202403241205_review] Prices for interval 24-Mar-2024 12:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1200 hrs on 24 March 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Mar-2024 12:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
115752PRICES SUBJECT TO REVIEW24/03/2024 11:55:18 AM

[EventId:202403241200_review] Prices for interval 24-Mar-2024 12:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1155 hrs on 24 March 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Mar-2024 12:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
115751PRICES SUBJECT TO REVIEW24/03/2024 11:50:23 AM

[EventId:202403241155_review] Prices for interval 24-Mar-2024 11:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1150 hrs on 24 March 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Mar-2024 11:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.