NON-CONFORMANCE Region QLD1 Monday, 11 December 2023
NON-CONFORMANCE QLD1 Region Monday, 11 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GSTONE5
Duration: 11/12/2023 10:30 to 11/12/2023 10:35
Amount: 15 MW
Constraint: NC-Q_GSTONE5
Auto-generated on behalf of Manager NEM Real Time Operations
NEM Local Temperature Alerts for VIC from 11 Dec 2023 to 15 Dec 2023
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
VIC
Mildura Ap (39+ Deg C): 12th Dec
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Network Augmentation Commissioned - SA Region - 10/12/2023
Network Augmentation Commissioned - SA Region - 10/12/2023
Commissioned: Robertstown - Bundey No. 1 275 kV Line
Bundey 275 kV Swtichyard
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Saturday, 9 December 2023
NON-CONFORMANCE NSW1 Region Saturday, 9 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BW03
Duration: 09/12/2023 17:50 to 09/12/2023 17:55
Amount: -44 MW
Constraint: NC-N_BW03
Auto-generated on behalf of Manager NEM Real Time Operations
Network Augmentation Commissioned - NSW Region - 08/12/2023
Network Augmentation Commissioned - NSW Region - 08/12/2023
Commissioned: Wellington - Wellington North Solar Farm 7H 330 kV Line
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 8 December 2023
NON-CONFORMANCE QLD1 Region Friday, 8 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: SWAN_E
Duration: 08/12/2023 17:05 to 08/12/2023 17:10
Amount: 20 MW
Constraint: NC-Q_SWAN_E
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202312081550_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 December 2023 15:50
Issued by Australian Energy Market Operator Ltd at 1550 hrs on 8 December 2023
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 December 2023.
Refer to market notice: 112094
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1550 hrs on 8 December 2023.
This is an AEMO autogenerated Market Notice.
[EventId:202312081450_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 December 2023 14:50
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 8 December 2023
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 December 2023.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1450 hrs on 8 December 2023.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region NSW1 Friday, 8 December 2023
NON-CONFORMANCE NSW1 Region Friday, 8 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: SUNTPSF1
Duration: 08/12/2023 12:35 to 08/12/2023 12:50
Amount: 76 MW
Constraint: NC-N_SUNTPSF1
Auto-generated on behalf of Manager NEM Real Time Operations