117363RECLASSIFY CONTINGENCY18/07/2024 05:31:28 PM

Reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines

Duration: 18/07/2024 17:30 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
117358RECLASSIFY CONTINGENCY18/07/2024 11:31:57 AM

Reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: Para-Templers West and Magill-Torrens Island A 275kV lines

Duration: 18/07/2024 11:30 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
117343NON-CONFORMANCE14/07/2024 04:50:19 PM

NON-CONFORMANCE Region QLD1 Sunday, 14 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 14 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 14/07/2024 16:35 to 14/07/2024 16:50
Amount: -66 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
117342NON-CONFORMANCE14/07/2024 01:45:18 AM

NON-CONFORMANCE Region VIC1 Sunday, 14 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Sunday, 14 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS1
Duration: 14/07/2024 01:40 to 14/07/2024 01:45
Amount: -35 MW
Constraint: NC-V_YWPS1

Auto-generated on behalf of Manager NEM Real Time Operations
117341RECLASSIFY CONTINGENCY13/07/2024 04:44:46 PM

Cancellation of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Cancellation time: 13/07/2024 16:44

Constraint set(s) revoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Refer AEMO Electricity Market Notice 117340

Auto-generated on behalf of Manager NEM Real Time Operations
117340RECLASSIFY CONTINGENCY13/07/2024 03:41:56 PM

Reclassification of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Duration: 13/07/2024 15:41 until further notice

Constraint set(s) invoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Auto-generated on behalf of Manager NEM Real Time Operations
117337NON-CONFORMANCE12/07/2024 07:55:20 AM

NON-CONFORMANCE Region QLD1 Friday, 12 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 12 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 12/07/2024 07:05 to 12/07/2024 07:55
Amount: -74 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
117324LOAD RESTORE08/07/2024 09:58:40 PM

Cancellation - Load Restoration Direction in the NSW Region - 08/07/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Load Restoration Direction in the NSW Region - 08/07/2024

Refer to AEMO Electricity Market Notice 117322
Load restoration as directed is complete. Direction cancelled from 2200 hrs 08/07/2024

Manager NEM Real Time Operations
117322LOAD RESTORE08/07/2024 07:34:37 PM

Load Restoration Direction in the NSW Region

AEMO ELECTRICITY MARKET NOTICE

Load Restoration Direction in the NSW Region

AEMO has directed load restoration commencing at 1930 hrs 08/07/2024
in the NSW region

The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.