113081RESERVE NOTICE06/01/2024 02:44:00 PM

STPASA - Update to the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113065 has been updated at 1400 hrs 06/01/2024 to the following:

1. From 1500 hrs 09/01/2024 to 1600 hrs 09/01/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1142 MW.

Manager NEM Real Time Operations
113066RESERVE NOTICE05/01/2024 02:57:09 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1730 hrs to 1800 hrs 10/01/2024.
The forecast capacity reserve requirement is 1568 MW.
The minimum capacity reserve available is 1560 MW.

AEMO Operations
113065RESERVE NOTICE05/01/2024 02:56:13 PM

STPASA - Update to the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113051 has been updated at 1400 hrs 05/01/2024 to the following:

1. From 1400 hrs to 1600 hrs 09/01/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 721 MW.

2. From 1630 hrs to 1800 hrs 09/01/2024.
The forecast capacity reserve requirement is 1612 MW.
The minimum capacity reserve available is 1258 MW.

AEMO Operations
113064MARKET SYSTEMS05/01/2024 02:37:24 PM

CHG0082511 | Pre-Production | Pre-Prod MSATS 50.0.4 LCCD Defect Release

Change Number: CHG0082511
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod MSATS 50.0.4 LCCD Defect Release
Change Start Date & Time: 09/01/2024 13:00:00 AEST
Change End Date & Time: 09/01/2024 17:00:00 AEST
Outage Start Date & Time: 09/01/2024 13:00:00 AEST
Outage End Date & Time: 09/01/2024 15:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
113051RESERVE NOTICE04/01/2024 03:05:46 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1430 hrs to 1600 hrs 09/01/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1119 MW.

AEMO Operations
113015MARKET SYSTEMS03/01/2024 01:57:46 PM

CHG0082504 | Pre-Production | Removal of support of TLS Version 1.1 and lower

Change Number: CHG0082504
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Market Network
Change Title: Removal of support of TLS Version 1.1 and lower
Change Start Date & Time: 14/02/2024 10:00:00 AEST
Change End Date & Time: 14/02/2024 14:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Pre-Production
Participant Impact and Requirements: Participants using TLS version 1.1 and lower, need to update their servers to use TLSv1.2 as a minimum. Failing to do so would impact the connectivity with AEMO. An outage is not expected but, there may be some minor interruptions during the change period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
112980GENERAL NOTICE02/01/2024 10:29:09 AM

NEM Local Temperature Alerts for VIC from 02 Jan 2024 to 06 Jan 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

VIC
Mildura Ap (39+ Deg C): 2nd Jan

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
112974GENERAL NOTICE01/01/2024 09:58:53 PM

Update - Lightning vulnerable equipment in QLD region

AEMO ELECTRICITY MARKET NOTICE.

Update - Lightning vulnerable equipment in QLD region

Special Reclassification of Transmission Equipment during lightning

Refer to AEMO Electricity Market Notice 112581 and 112884.

At 1424 hrs 21/12/2023, the Middle Ridge 275 kV circuit breakers 5432 and 5422 tripped. This offloaded the H14 Middle Ridge No.2 and No. 3 275/110 kV transformers

The cause of the trip was identified as due to lightning.

In accordance with SO_OP_3715, AEMO now considers the H14 Middle Ridge No. 2 and No. 3 275/110 kV transformers to be vulnerable due to lightning.

Manager NEM Real Time Operations
112942GENERAL NOTICE31/12/2023 04:00:58 PM

Cancellation of Minimum System Load 1 (MSL1) in the VIC Region on 31/12/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation - MSL1 - VIC Region

Refer Market Notice 112936

The MSL1 condition for 31/12/2023 is cancelled at 1600 hrs 31/12/2023

Manager NEM Real Time Operations