Market Notices

117381INTER-REGIONAL TRANSFER20/07/2024 01:03:16 PM

Inter-regional transfer limit variation - Mitchell Singleton 95X 132kV LINE- NSW region - 20/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Mitchell Singleton 95X 132kV LINE- NSW region - 20/07/2024

At 1117 hrs 20/07/2024 there was an unplanned outage of Mitchell Singleton 95X 132kV LINE.

The following constraint set(s) invoked at 1250 hrs 20/07/2024
N-NIL_RBKU_CLOSED
N-LDTM_82_CL

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
117375INTER-REGIONAL TRANSFER19/07/2024 07:03:12 PM

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).

AEMO ELECTRICITY MARKET NOTICE

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).

Refer AEMO Electricity Market Notice 117372

AEMO has been notified that the controls to vary Directlink output are now available.

Constraint set I-CTRL_ISSUE_TE revoked at 1835 hrs.

Manager NEM Real Time Operations
117374INTER-REGIONAL TRANSFER19/07/2024 06:01:53 PM

Inter-regional transfer limit variation - Heywood interconnector - SA and Vic regions - 19/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Heywood interconnector - SA and Vic regions- 19/07/2024

Refer to reclassification Market notice 117373

The following constraint set(s) invoked at 1740 hrs 19/07/2024
I-SV_250 , I-VS_250

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA

Manager NEM Real Time Operations
117372INTER-REGIONAL TRANSFER19/07/2024 04:41:55 PM

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO has been notified that the controls to vary Directlink output are unavailable until further notice.

Constraint set I-CTRL_ISSUE_TE invoked from 1640 hrs.

The constraint set contains equations with the following interconnector on the LHS:

N-Q-MNSP1


Manager NEM Real Time Operations
117371INTER-REGIONAL TRANSFER19/07/2024 04:20:09 PM

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).

AEMO ELECTRICITY MARKET NOTICE

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).

Refer AEMO Electricity Market Notice 117368

AEMO has been notified that the controls to vary Directlink output are now available.

Constraint set I-CTRL_ISSUE_TE revoked at 1620 hrs.

Manager NEM Real Time Operations
117368INTER-REGIONAL TRANSFER19/07/2024 03:24:41 PM

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO has been notified that the controls to vary Directlink output are unavailable until further notice.

Constraint set I-CTRL_ISSUE_TE invoked from 1530 hrs.

The constraint set contains equations with the following interconnector on the LHS:

N-Q-MNSP1


Manager NEM Real Time Operations
117356GENERAL NOTICE18/07/2024 09:06:38 PM

Network Augmentation Commissioned - VIC Region - 18/07/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - VIC Region - 18/07/2024

At 2044 hrs 18,07/2024, Cressy Terminal Station has been cut into the existing Moorabool - Haunted Gully No.1 500 kV line to form the following circuits:

Cressy - Haunted Gully No 1 500 kV line
Cressy - Moorabool No 1 500 kV line

Manager NEM Real Time Operations
117355INTER-REGIONAL TRANSFER16/07/2024 04:09:23 PM

Inter-regional transfer limit variation -Tungkillo-Tailem_Bnd 1 275kV LINE - SA region - 16/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Tungkillo-Tailem_Bnd 1 275kV LINE - SA region - 16/07/2024

A planned outage of Tungkillo-Tailem_Bnd 1 275kV LINE in the SA region was scheduled from 0845 hrs 16/07/2024 to 1630 hrs 16/07/2024.

The outage has been completed and Tungkillo-Tailem_Bnd 1 275kV LINE returned to service at 1255 hrs 16/07/2024

Constraint set(s) revoked: S-TBTU

Manager NEM Real Time Operations
117339INTER-REGIONAL TRANSFER12/07/2024 09:00:58 PM

Inter-regional transfer limit variation - Robertstown - Tungkillo No.1 275 kV line - SA region - 12/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Robertstown - Tungkillo No.1 275 kV line - SA region - 12/07/2024

A planned outage of Robertstown - Tungkillo No.1 275 kV line in the SA region was scheduled to be completed at 1730 hrs 14/07/2024.

The outage has been completed and Robertstown - Tungkillo No.1 275 kV line returned to service at 2043 hrs 12/07/2024

Constraint set(s) revoked: S-RBTU

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm