Filter by category
Filter by Date
Minimum System Load 1 (MSL1) in the VIC Region on 28/09/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1100 hrs to 1400 hrs 28/09/2024.
Minimum regional demand is forecast to be 1638 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1865 MW
- MSL2 - 1365 MW
- MSL3 - 865 MW
MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.
Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem
AEMO is seeking a market response.
An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in actions such as recalling network outages, the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.
AEMO Operations
Inter-regional transfer limit variation -South East to Tailem Bend No 1 275 KV Line - SA region - 17/09/2024
Inter-regional transfer limit variation - South East to Tailem Bend No 1 275 KV Line - SA region - 17/09/2024
At 1034 hrs 17/09/2024 there was a short notice outage of South East to Tailem Bend No 1 275 KV Line.
The following constraint set(s) invoked at 1035 hrs 20/09/2024
S-TBSE,
S-BC_CP
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,NSW1-QLD1,T-V-MNSP1,V-S-MNSP1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 16/09/2024
Cancellation of Actual (LOR1) condition in the NSW region - 16/09/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.118298 is cancelled at 1915 hrs 16/09/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/09/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/09/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 1274 MW
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Braemar No2 330 kV / 275 kV Transformer. - QLD region - 14/09/2024
Inter-regional transfer limit variation - Braemar No2 330 kV / 275 kV Transformer. - QLD region - 14/09/2024
At 1320 hrs 14/09/2024 there was a short notice outage of Braemar No2 330 kV / 275 kV Transformer.
The following constraint set(s) invoked at 1320 hrs 14/09/2024
Q-BRTX2
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 KV Line - NSW region - 13/09/2024
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 KV Line - NSW region - 13/09/2024
A planned outage of Armidale - Sapphire 8E 330 KV Line in the NSW region was scheduled from 1630 hrs 11/09/2024 to 1330 hrs 14/09/2024.
The outage has been completed and Armidale - Sapphire 8E 330 KV Line returned to service at 1600 hrs 13/09/2024
Constraint set(s) revoked: N-ARSR_8E, N-TW_SVC
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 KV Line - NSW region - 13/09/2024
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 KV Line - NSW region - 13/09/2024
A planned outage of Armidale - Sapphire 8E 330 KV Line in the NSW region was scheduled from 1630 hrs 11/09/2024 to 1330 hrs 13/09/2024.
The outage has been rescheduled for 1630 hrs 11/09/2024 to 1330 hrs 14/09/2024.
Constraint sets invoked: N-ARSR_8E, N-TW_SVC, N-DM_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Murraylink - SA region - 12/09/2024
Inter-regional transfer limit variation - Murraylink - SA region - 12/09/2024
A planned outage of Murraylink in the SA region was scheduled from 1030 hrs 12/09/2024 to 1630 hrs 12/09/2024.
The outage has been completed and Murraylink returned to service at 1235 hrs 12/09/2024
Constraint set(s) revoked: I-MURRAYLINK
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 KV Line - NSW region - 12/09/2024
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 KV Line - NSW region - 12/09/2024
A planned outage of Armidale - Sapphire 8E 330 KV Line in the NSW region was scheduled from 1630 hrs 11/09/2024 to 0900 hrs 16/09/2024.
The outage has been rescheduled for 1630 hrs 11/09/2024 to 1330 hrs 13/09/2024.
Constraint sets invoked: N-ARSR_8E, N-TW_SVC, N-DM_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations