Filter by category
Filter by Date
STPASA - Forecast Minimum System Load 1 (MSL1) in the VIC Region on 13/10/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1100 hrs 13/10/2024 to 1400 hrs 13/10/2024.
Minimum regional demand is forecast to be 1623 MW at 1300 hrs, and the advisory threshold is:
o MSL1 - 1865 MW
o MSL2 - 1365 MW
o MSL3 - 865 MW
MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.
AEMO Operations
Inter-regional transfer limit variation - Bannaby -Sydney West 39 330 kV line - NSW region - 03/10/2024
Inter-regional transfer limit variation - Bannaby -Sydney West 39 330 kV line- NSW region - 03/10/2024
A planned outage of Bannaby -Sydney West 39 330 kV line in the NSW region was scheduled from 0700 hrs 16/09/2024 to 1600 hrs 11/10/2024.
The outage has been completed and Bannaby -Sydney West 39 330 kV line returned to service at 0920 hrs 03/10/2024
Constraint set revoked: N-BYSW_39_15M
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Stockdill - Upper Tumut 1 330 kV line- NSW region - 29/09/2024
Inter-regional transfer limit variation - Stockdill - Upper Tumut 1 330 kV line - NSW region - 29/09/2024
At 0313 hrs 29/09/2024 there was an unplanned outage of Stockdill - Upper Tumut 1 330 kV line.
The following constraint set invoked at 0320 hrs 29/09/2024
N-SDUT_1
This constraint set contains equations with the following interconnectors on the LHS.
V-S-MNSP1
VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation - MSL1- VIC Region at 1430 hrs 28/09/2024.
Cancellation - MSL1- VIC Region at 1430 hrs 28/09/2024.
Refer to Market Notice 118475.
Manager NEM Real Time Operations
Cancellation - MSL1- VIC Region at 1530 hrs 27/09/2024.
Cancellation - MSL1- VIC Region at 1530 hrs 27/09/2024.
Refer to Market Notice 118442 for MSL1.
Manager NEM Real Time Operations
Minimum System Load 1 (MSL1) in the VIC Region on 28/09/2024
Update to Market Notice 118421.
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1030 hrs to 1430 hrs 28/09/2024.
Minimum regional demand is forecast to be 1420 MW at 1200 hrs, and the advisory threshold is:
- MSL1 - 1865 MW
- MSL2 - 1365 MW
- MSL3 - 865 MW
MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.
Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem
AEMO is seeking a market response.
An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in action such as the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.
AEMO Operations
Minimum System Load 1 (MSL1) in the VIC Region on 27/09/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1300 hrs 27/09/2024 to 1330 hrs 27/09/2024.
Minimum regional demand is forecast to be 1879 MW at 1330 hrs, and the advisory threshold is:
o MSL1 - 1915 MW
o MSL2 - 1415 MW
o MSL3 - 915 MW
MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.
Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem
AEMO is seeking a market response.
An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in action such as the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.
AEMO Operations
Minimum System Load 1 (MSL1) in the VIC Region on 28/09/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1100 hrs to 1400 hrs 28/09/2024.
Minimum regional demand is forecast to be 1638 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1865 MW
- MSL2 - 1365 MW
- MSL3 - 865 MW
MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.
Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem
AEMO is seeking a market response.
An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in actions such as recalling network outages, the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.
AEMO Operations
Inter-regional transfer limit variation -South East to Tailem Bend No 1 275 KV Line - SA region - 17/09/2024
Inter-regional transfer limit variation - South East to Tailem Bend No 1 275 KV Line - SA region - 17/09/2024
At 1034 hrs 17/09/2024 there was a short notice outage of South East to Tailem Bend No 1 275 KV Line.
The following constraint set(s) invoked at 1035 hrs 20/09/2024
S-TBSE,
S-BC_CP
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,NSW1-QLD1,T-V-MNSP1,V-S-MNSP1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations