Market Notices

115160RESERVE NOTICE26/02/2024 05:43:39 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 26/02/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 26/02/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 2030 hrs

The capacity reserve requirement is 922 MW
The minimum capacity reserve available is 706 MW

Manager NEM Real Time Operations
115048RESERVE NOTICE23/02/2024 04:46:12 PM

Cancellation of Actual (LOR1) condition in the NSW region - 23/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 23/02/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.115047 is cancelled at 1645 hrs 23/02/2024.

Manager NEM Real Time Operations
115047RESERVE NOTICE23/02/2024 04:12:17 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 23/02/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 23/02/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1600 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs

The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1252 MW

Manager NEM Real Time Operations
114930RESERVE NOTICE21/02/2024 07:45:35 PM

Cancellation of Actual (LOR1) condition in the SA region - 21/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the SA region - 21/02/2024

The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.114929 is cancelled at 1945 hrs 21/02/2024.

Manager NEM Real Time Operations
114929RESERVE NOTICE21/02/2024 07:22:43 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 21/02/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 21/02/2024

Refer AEMO Electricity Market Notice 114927

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1900 hrs.
The Actual LOR1 condition is not forecast in Pre Dispatch

The capacity reserve requirement is 428 MW
The minimum capacity reserve available is 277 MW

Manager NEM Real Time Operations
114927RESERVE NOTICE21/02/2024 06:47:19 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 21/02/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 21/02/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1830 hrs.
The Actual LOR1 condition is not forecast in Pre Dispatch

The capacity reserve requirement is 431 MW
The minimum capacity reserve available is 414 MW

Manager NEM Real Time Operations
114759POWER SYSTEM EVENTS15/02/2024 02:06:23 PM

Update: Significant power system event - Victoria Region - Hazelwood transformers and Hazelwood PS - Jeeralang No 2 220kV -13/02/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Significant power system event - 13/02/2024

Refer AEMO Electricity Market Notices 114685

At 1247 hrs 15/02/2024 the Hazelwood PS - Jeeralang No 2 220kV line was returned to service in the Victoria region

All of the equipment has now been returned to service.

The cause of this significant power system event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
114718PRICE ADJUSTMENT14/02/2024 02:52:11 PM

[EventId:202402131320_confirmed] Prices for interval 13-Feb-2024 13:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1452 hrs on 14 February 2024

PRICES ARE NOW CONFIRMED for trading interval 13-Feb-2024 13:20.

In accordance with Market Notice 114583 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
- Over-Constrained Dispatch has been resolved for dispatch interval

Changed Prices ($/MWh)

TYPE
Region Original Adjusted
Price Price
ENERGY
NSW1 -$38.41 -$35.04
QLD1 -$40.60 -$36.57
LOWERREG
TAS1 $16,600.00 $9.88
RAISEREG
TAS1 $16,600.00 $150.68


This is an AEMO autogenerated Market Notice.
114685POWER SYSTEM EVENTS13/02/2024 10:37:34 PM

Update: Significant power system event - Victoria Region - Hazelwood transformers -13/02/2024

AEMO ELECTRICITY MARKET NOTICE.

At 1827 hrs 13/02/2024 At Hazelwood terminal station in the Victoria region, the following plant was returned to service.

The No1 500 kV / 220 kV transformer
The No2 500 kV / 220 kV transformer
The No3 500 kV / 220 kV transformer
The No4 500 kV / 220 kV transformer

The Jeeralang - Hazelwood No 2 220kV line remains out of service.

Refer to Network outage scheduler (NOS) for further details.

Refer Market notice 114641 and 114643

This Market Notice is issued in accordance with NER clause 4.8.3.


Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm