Filter by category
Filter by Date
Update - Lightning vulnerable lines in TAS region
Update - Lightning vulnerable lines in TAS region
Refer to AEMO Electricity Market Notice 118320 ,118321, 118322
At 1340 hrs 19/09/2024 the Gordon - Chapel St No 1 220 kV line and the Gordon - Chapel St No 2 220 kV line tripped.
The cause of the trip was identified as due to Lightning.
In accordance with SO_OP_3715, AEMO now considers the Gordon - Chapel St No 1 220 kV line and the Gordon - Chapel St No 2 220 kV line to be vulnerable with a category of Vulnerability due to Lightning.
Manager NEM Real Time Operations
Update to system normal constraint equation in NSW for transient voltage stability in south-west NSW
Refer to market notice 92840.
Transgrid has advised AEMO of an update to the transient voltage stability limit in south-west NSW for loss of Darlington Point to Wagga (63) 330 kV line. The limit will include terms for the Darlington Point and Riverina BESS.
The following constraint equation will be updated with the above changes at 1100 hrs Friday 20th September 2024.
N::N_NIL_63
For full details on the formulation, the new constraint equation has now been loaded into AEMO's pre-production systems.
For further details on these constraint equation please contact ben.blake@aemo.com.au
Ben Blake
AEMO Operations
Update - Non-credible contingency event - TAS region - 19/09/2024
Update - Non-credible contingency event - TAS region - 19/09/2024
Refer AEMO Electricity Market Notice 118321
At 1446 hrs the Gordon - Chapel St No 1 and No 2 220 kV lines were returned to service.
This non-credible contingency event was caused by lightning. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Manager NEM Real Time Operations
Update - Non-credible contingency event - TAS region - 19/09/2024
Update - Non-credible contingency event - TAS region - 19/09/2024
At 1340 hrs the Gordon - Chapel St No1 and No 2 220 kV lines tripped.
AEMO did not instruct load shedding.
AEMO has advised of approximately 112 MW disconnection of bulk electrical load,
disconnection of generation at Studland Bay Wind generator (71 MW) and 23 MW generation reduction at Gordon Power station.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Non-credible contingency event - TAS region - 19/09/2024
Non-credible contingency event - TAS region - 19/09/2024
At 1340 hrs the Gordon - Chapel St No1 and No 2 220 kV lines tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Planned outage of Tailem Bend - South East 275 kV transmission line in the South Australia region beginning on 20/09/2024
The Tailem Bend - South East No 1 275 kV line in the South Australian (SA) region is planned to be out of service from 2100 hrs on 20/09/2024 to 0530 hrs on 21/09/2024.
A credible contingency event during this planned outage could cause synchronous separation of the SA region from the rest of the NEM.
During this planned outage:
- Power transfer will be restricted across the VIC - SA interconnector (Heywood interconnector); and
- Post contingent FCAS will be sourced within SA following Separation event.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
NON-CONFORMANCE Region SA1 Wednesday, 18 September 2024
NON-CONFORMANCE SA1 Region Wednesday, 18 September 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 18/09/2024 11:20 to 18/09/2024 12:50
Amount: 21 MW
Constraint: NC-S_TB2HYB_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Tuesday, 17 September 2024
NON-CONFORMANCE SA1 Region Tuesday, 17 September 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MANNSF2
Duration: 17/09/2024 14:10 to 17/09/2024 15:00
Amount: 23 MW
Constraint: NC-S_MANNSF2
Auto-generated on behalf of Manager NEM Real Time Operations
Network Augmentation Commissioned - NSW Region - 10/09/2024
Network Augmentation Commissioned - NSW Region - 10/09/2024
At 1750 hrs, the following equipment at Buronga 330 kV substation has been commissioned:
1) Buronga 330 kV A bus.
2) Buronga 330 kV B bus.
3) Buronga No 1 330 kV capacitor.
4) Buronga No 2 330 kV capacitor.
5) Buronga No 7 330/220 kV transformer.
Manager NEM Real Time Operations