Filter by category
Filter by Date
[EventId:200] AP STARTED for ENERGY in NSW1 at 11 May 2024 03:55
Issued by Australian Energy Market Operator Ltd at 0355 hrs on 11 May 2024
ADMINISTERED PRICE PERIOD DECLARED in NSW1 region.
AEMO has determined that the rolling sum of the uncapped spot prices for the NSW1 region over the previous 2016 trading intervals has exceeded the cumulative price threshold (CPT) of $1,490,200.00.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO has determined that an administered price period will commence at the trading interval starting 0405 hrs on 11 May 2024 and will continue through to the end of that trading day.
An administered price cap (APC) of 600 $/MWh will apply to all trading intervals during this administered price period. This APC will apply to spot prices and to all market ancillary service prices in the NSW1 region.
An administered floor price (AFP) of -600 $/MWh will apply to spot prices.
AEMO will continue to monitor the rolling sum of the uncapped spot prices and issue further Market Notices as required.
This is an AEMO autogenerated Market Notice.
[EventId:199] AP ENDED for ENERGY in NSW1 at 11 May 2024 03:55
Issued by Australian Energy Market Operator Ltd at 0355 hrs on 10 May 2024
ADMINISTERED PRICE PERIOD ENDS in NSW1 region.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO is notifying market participants that the administered price period declared for the NSW1 region in market notice 116570 will end at 0400 hrs on 11 May 2024.
This is an AEMO autogenerated Market Notice.
[EventId:199] AP STARTED for ENERGY in NSW1 at 10 May 2024 03:55
Issued by Australian Energy Market Operator Ltd at 0355 hrs on 10 May 2024
ADMINISTERED PRICE PERIOD DECLARED in NSW1 region.
AEMO has determined that the rolling sum of the uncapped spot prices for the NSW1 region over the previous 2016 trading intervals has exceeded the cumulative price threshold (CPT) of $1,490,200.00.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO has determined that an administered price period will commence at the trading interval starting 0405 hrs on 10 May 2024 and will continue through to the end of that trading day.
An administered price cap (APC) of 600 $/MWh will apply to all trading intervals during this administered price period. This APC will apply to spot prices and to all market ancillary service prices in the NSW1 region.
An administered floor price (AFP) of -600 $/MWh will apply to spot prices.
AEMO will continue to monitor the rolling sum of the uncapped spot prices and issue further Market Notices as required.
This is an AEMO autogenerated Market Notice.
[EventId:198] AP ENDED for ENERGY in NSW1 at 10 May 2024 03:55
Issued by Australian Energy Market Operator Ltd at 0355 hrs on 09 May 2024
ADMINISTERED PRICE PERIOD ENDS in NSW1 region.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO is notifying market participants that the administered price period declared for the NSW1 region in market notice 116554 will end at 0400 hrs on 10 May 2024.
This is an AEMO autogenerated Market Notice.
[EventId:198] AP STARTED for ENERGY in NSW1 at 09 May 2024 03:55
Issued by Australian Energy Market Operator Ltd at 0355 hrs on 09 May 2024
ADMINISTERED PRICE PERIOD DECLARED in NSW1 region.
AEMO has determined that the rolling sum of the uncapped spot prices for the NSW1 region over the previous 2016 trading intervals has exceeded the cumulative price threshold (CPT) of $1,490,200.00.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO has determined that an administered price period will commence at the trading interval starting 0405 hrs on 09 May 2024 and will continue through to the end of that trading day.
An administered price cap (APC) of 600 $/MWh will apply to all trading intervals during this administered price period. This APC will apply to spot prices and to all market ancillary service prices in the NSW1 region.
An administered floor price (AFP) of -600 $/MWh will apply to spot prices.
AEMO will continue to monitor the rolling sum of the uncapped spot prices and issue further Market Notices as required.
This is an AEMO autogenerated Market Notice.
[EventId:197] AP ENDED for ENERGY in NSW1 at 09 May 2024 03:55
Issued by Australian Energy Market Operator Ltd at 0355 hrs on 08 May 2024
ADMINISTERED PRICE PERIOD ENDS in NSW1 region.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO is notifying market participants that the administered price period declared for the NSW1 region in market notice 116550 will end at 0400 hrs on 09 May 2024.
This is an AEMO autogenerated Market Notice.
[EventId:197] AP STARTED for ENERGY in NSW1 at 08 May 2024 19:45
Issued by Australian Energy Market Operator Ltd at 1945 hrs on 08 May 2024
ADMINISTERED PRICE PERIOD DECLARED in NSW1 region.
AEMO has determined that the rolling sum of the uncapped spot prices for the NSW1 region over the previous 2016 trading intervals has exceeded the cumulative price threshold (CPT) of $1,490,200.00.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO has determined that an administered price period will commence at the trading interval starting 1955 hrs on 08 May 2024 and will continue through to the end of that trading day.
An administered price cap (APC) of 600 $/MWh will apply to all trading intervals during this administered price period. This APC will apply to spot prices and to all market ancillary service prices in the NSW1 region.
An administered floor price (AFP) of -600 $/MWh will apply to spot prices.
AEMO will continue to monitor the rolling sum of the uncapped spot prices and issue further Market Notices as required.
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - Blyth West to Munno Para 275 kV line - SA region - 08/05/2024
Inter-regional transfer limit variation - Blyth West to Munno Para 275 kV line - SA region - 08/05/2024
At 1536 hrs 08/05/2024 there was an unplanned outage of Blyth West to Munno Para 275 kV line.
The following constraint set(s) invoked at 1545 hrs 08/05/2024
S-X_BGBW+BWMP
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Tamworth No. 1 330 kV Bus - NSW region - 08/05/2024
Inter-regional transfer limit variation - Tamworth No. 1 330 kV Bus - NSW region - 08/05/2024
A planned outage of Tamworth No. 1 330 kV Bus in the NSW region was scheduled from 1200 hrs 08/05/2024 to 1800 hrs 10/05/2024.
The outage has been cancelled at 1154 hrs 08/05/2024
Constraint set(s) revoked: N-TW_330_BUS1, N-LDTW_84
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1
N-Q-MNSP1
T-V-MNSP1
Manager NEM Real Time Operations