Market Notices

117239INTER-REGIONAL TRANSFER28/06/2024 02:07:43 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 28/06/2024

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the VIC region, AEMO has invoked automated constraint set CA_SYDS_5590C0E2 from 1355hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

V-S-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
117200INTER-REGIONAL TRANSFER26/06/2024 02:36:10 PM

Inter-regional transfer limit variation - Heywood - South East No 2 275 kV Line - SA region - 26/06/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -Heywood - South East No 2 275 kV Line SA region - 26/06/2024

A planned outage of Heywood - South East No 2 275 kV Line in the SA region was scheduled from 0815 hrs 26/06/2024 to 1930 hrs 26/06/2024.

The outage has been completed and Heywood - South East No 2 275 kV Line returned to service at 1410 hrs 26/06/2024

Constraint set(s) revoked:
I-HYSE
I-VS_050
I-VS+LKB_050

Manager NEM Real Time Operations
117133INTER-REGIONAL TRANSFER25/06/2024 10:28:52 AM

Inter-regional transfer limit variation -Hazelwood - South Morang No 1 500 kV Line - VIC region - 25/06/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hazelwood - South Morang No 1 500 kV Line - VIC region - 25/06/2024

A planned outage of Hazelwood - South Morang No 1 500 kV Line in the VIC region was scheduled from 0800 hrs 25/06/2024 to 1530 hrs 25/06/2024.

The outage has been completed and Hazelwood - South Morang No 1 500 kV Line returned to service at 1016 hrs 25/06/2024

Constraint set(s) revoked: V-HWSM

Manager NEM Real Time Operations
117087RESERVE NOTICE20/06/2024 07:41:48 PM

Cancellation of Actual (LOR1) condition in the NSW region - 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 20/06/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.117086 is cancelled at 1930hrs 20/06/2024.

Manager NEM Real Time Operations
117086RESERVE NOTICE20/06/2024 06:13:43 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 20/06/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1726 MW
The minimum capacity reserve available is 1695 MW

Manager NEM Real Time Operations
117078INTER-REGIONAL TRANSFER19/06/2024 05:27:58 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 1 Leg of Directlink .

The following constraint set was invoked at 1725 hrs 19/06/2024

N-X_MBTE_2

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
117053INTER-REGIONAL TRANSFER18/06/2024 03:19:21 PM

Inter-regional transfer limit variation - Collector Wind Farm to Yass 3L 330kV line - NSW region - 18/06/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Collector Wind Farm to Yass 3L 330kV line - NSW region - 18/06/2024

A planned outage of Collector Wind Farm to Yass 3L 330kV line in the NSW region was scheduled from 0600 hrs 03/04/2024 to 1500 hrs 08/07/2024.

The outage has been completed and Collector Wind Farm to Yass 3L 330kV line returned to service at 1515 hrs 18/06/2024

Constraint set revoked: N-CTYS_3L_WG_CLOSE

Manager NEM Real Time Operations
117021RESERVE NOTICE15/06/2024 08:03:58 PM

Cancellation of Actual (LOR1) condition in the NSW region - 15/06/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 15/06/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.117020 is cancelled at 1900 hrs 15/06/2024.

Manager NEM Real Time Operations
117020RESERVE NOTICE15/06/2024 05:14:10 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/06/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/06/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1780 MW
The minimum capacity reserve available is 1446 MW

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm