Filter by category
Filter by Date
[EventId:202411211810_confirmed] Prices for interval 21-Nov-2024 18:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 21 November 2024
PRICES ARE NOW CONFIRMED for trading interval 21-Nov-2024 18:10.
In accordance with Market Notice 120767 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411211805_confirmed] Prices for interval 21-Nov-2024 18:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 21 November 2024
PRICES ARE NOW CONFIRMED for trading interval 21-Nov-2024 18:05.
In accordance with Market Notice 120765 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411211800_confirmed] Prices for interval 21-Nov-2024 18:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 21 November 2024
PRICES ARE NOW CONFIRMED for trading interval 21-Nov-2024 18:00.
In accordance with Market Notice 120764 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411211750_confirmed] Prices for interval 21-Nov-2024 17:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 21 November 2024
PRICES ARE NOW CONFIRMED for trading interval 21-Nov-2024 17:50.
In accordance with Market Notice 120762 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region NSW1 Thursday, 21 November 2024
NON-CONFORMANCE NSW1 Region Thursday, 21 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 21/11/2024 01:55 to 21/11/2024 02:10
Amount: -20 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
Network Augmentation Commissioned - QLD Region - 21/11/2024
Network Augmentation Commissioned - QLD Region - 21/11/2024
Commissioned:
Belmont No.2 275 kV 150 MVar reactor
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 20 November 2024
NON-CONFORMANCE QLD1 Region Wednesday, 20 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 20/11/2024 06:35 to 20/11/2024 15:35
Amount: -45 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Project Energy Connect (PEC-1) testing 21st November 2024 0600-0900 for flows in both directions
Refer to market notice 120307
There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 50 MW on 21st November from 06:00hrs to 09:00hrs
This test includes includes a fast runback of Murraylink.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Ben Blake
AEMO Operations
Request for Generator Recall Information for the period from 25/11/2024 to 26/11/2024 for NSW Region
Refer to AEMO Electricity Market Notice no. 120700, 120699 and 120698.
Please provide Generator Recall Information for the period from 25/11/2024 to 26/11/2024, by 1200 hrs on 21/11/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations