Filter by category
Filter by Date
Heywood testing (Vic to SA) 16th October 2024
There is an opportunity for testing Heywood Interconnector (HIC) flow from Victoria to South Australia above 450MW on 16th October from 17:00hrs to 20:00hrs
This test includes a trip and reclose of a line in South Australia.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Ben Blake
AEMO Operations
NEM Local Temperature Alerts for SA from 16 Oct 2024 to 20 Oct 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 16th Oct, 17th Oct
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/10/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 118869 is cancelled at 1100 hrs 14/10/2024.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
NEM Local Temperature Alerts for SA from 14 Oct 2024 to 18 Oct 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 17th Oct
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/10/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1730 hrs to 1930 hrs 16/10/2024.
The forecast capacity reserve requirement is 1456 MW.
The minimum capacity reserve available is 1407 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Heywood testing (SA to Vic) 11th October 2024
There is an opportunity for testing Heywood Interconnector (HIC) flow from South Australia to Victoria above 450MW and Victoria to South Australia above 450MW on 11th October from 8:00hrs to 19:00hrs
This test includes a trip and reclose of a line in South Australia.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Ben Blake
AEMO Operations
Managing outages that create a credible risk of SA islanding
From 9th Oct 2024 AEMO will change constraints used during outages that create a credible risk of SA islanding.
From this date AEMO will:
1) Increase the maximum allowable flow on the V-SA interconnector from 50 MW to 250 MW in the VIC to SA direction, where the transmission outages is a planned outage.
2) Operate the SA region to the default 49-51 Hz target frequency containment band following a contingency event resulting in actual SA islanding. In order to meet this requirement, AEMO may now procure Contingency Raise FCAS locally from the SA region during these outages.
These changes reflect updated advice received by AEMO from the SA Jurisdictional System Security Coordinator.
The first network outage affected by this change is planned for 14th October 2024.
Andrew Groom
AEMO Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/10/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 118644 is cancelled at 1415 hrs 07/10/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/10/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Periods:
[1.] From 1530 hrs 08/10/2024 to 1600 hrs 08/10/2024.
The forecast capacity reserve requirement is 719 MW.
The minimum capacity reserve available is 615 MW.
[2.] From 1730 hrs 08/10/2024 to 1900 hrs 08/10/2024.
The forecast capacity reserve requirement is 692 MW.
The minimum capacity reserve available is 475 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations