Market Notices

120305POWER SYSTEM EVENTS12/11/2024 10:55:18 AM

Non-credible contingency event - VIC region - 12/11/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 12/11/2024

At 1041 hrs the Yallourn No 1 220 kV bus and Yallourn Unit 4 tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.


The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
120284PRICES SUBJECT TO REVIEW11/11/2024 05:55:18 PM

[EventId:202411111800_review] Prices for interval 11-Nov-2024 18:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1755 hrs on 11 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Nov-2024 18:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120281PRICES SUBJECT TO REVIEW11/11/2024 05:50:19 PM

[EventId:202411111755_review] Prices for interval 11-Nov-2024 17:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1750 hrs on 11 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Nov-2024 17:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120280PRICES SUBJECT TO REVIEW11/11/2024 05:45:25 PM

[EventId:202411111750_review] Prices for interval 11-Nov-2024 17:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1745 hrs on 11 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Nov-2024 17:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120279PRICES SUBJECT TO REVIEW11/11/2024 05:40:15 PM

[EventId:202411111745_review] Prices for interval 11-Nov-2024 17:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1740 hrs on 11 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Nov-2024 17:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120278PRICES SUBJECT TO REVIEW11/11/2024 05:35:16 PM

[EventId:202411111740_review] Prices for interval 11-Nov-2024 17:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1735 hrs on 11 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Nov-2024 17:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120277PRICES SUBJECT TO REVIEW11/11/2024 05:30:16 PM

[EventId:202411111735_review] Prices for interval 11-Nov-2024 17:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 11 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Nov-2024 17:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120276GENERAL NOTICE11/11/2024 05:07:24 PM

Project Energy Connect (PEC-1) testing 12th November 2024 for flows in both directions

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 120016

There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 50 MW on 12th November from 06:00hrs to 11:00hrs

This test includes the synchronization of the new PEC Stage 1 interconnector and testing of the Phase Shifting transformer at Buronga substation.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Ben Blake
AEMO Operations
     
120260PRICES SUBJECT TO REVIEW11/11/2024 02:05:15 PM

[EventId:202411111410_review] Prices for interval 11-Nov-2024 14:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1405 hrs on 11 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Nov-2024 14:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs