Market Notices

114932NON-CONFORMANCE22/02/2024 05:55:17 AM

NON-CONFORMANCE Region VIC1 Thursday, 22 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Thursday, 22 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MERCER01
Duration: 22/02/2024 05:40 to 22/02/2024 05:55
Amount: 127 MW
Constraint: NC-V_MERCER01

Auto-generated on behalf of Manager NEM Real Time Operations
114931NON-CONFORMANCE22/02/2024 04:30:13 AM

NON-CONFORMANCE Region NSW1 Thursday, 22 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 22 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP6
Duration: 22/02/2024 04:20 to 22/02/2024 04:30
Amount: -29 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations
114923MARKET INTERVENTION21/02/2024 04:36:24 PM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0030 hrs 23/02/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
114921MARKET INTERVENTION21/02/2024 04:30:12 PM

Direction - SA region 21/02/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 21/02/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1635 hrs on 21/02/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
114918MARKET INTERVENTION21/02/2024 02:51:14 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 114916

The synchronous generating units currently expected to be synchronised in SA from 0700 hrs 22/02/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1630 hrs 21/02/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
114916MARKET INTERVENTION21/02/2024 01:14:53 PM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0800 hrs 22/02/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
114912NON-CONFORMANCE21/02/2024 05:16:04 AM

NON-CONFORMANCE Region QLD1 Wednesday, 21 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 21 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YABULU2
Duration: 21/02/2024 04:30 to 21/02/2024 05:15
Amount: 41 MW
Constraint: NC-Q_YABULU2

Auto-generated on behalf of Manager NEM Real Time Operations
114911NON-CONFORMANCE21/02/2024 05:15:13 AM

NON-CONFORMANCE Region QLD1 Wednesday, 21 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 21 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YABULU
Duration: 21/02/2024 04:30 to 21/02/2024 05:15
Amount: 75 MW
Constraint: NC-Q_YABULU

Auto-generated on behalf of Manager NEM Real Time Operations
114894NON-CONFORMANCE20/02/2024 05:15:16 PM

NON-CONFORMANCE Region NSW1 Tuesday, 20 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 20 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MP2
Duration: 20/02/2024 17:10 to 20/02/2024 17:15
Amount: 27 MW
Constraint: NC-N_MP2

Auto-generated on behalf of Manager NEM Real Time Operations