Filter by category
Filter by Date
[EventId:202405011710_review] Prices for interval 01-May-2024 17:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 1 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 01-May-2024 17:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404301730_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 30 April 2024 17:30
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 30 April 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 April 2024.
Refer to market notice: 116390
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1730 hrs on 30 April 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202404301630_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 30 April 2024 16:30
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 30 April 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 April 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1630 hrs on 30 April 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Planned outage of Gordon - Chapel St No. 1 220 kV line in the TAS region on 26/04/2024
The Gordon - Chapel St No. 1 220 kV line in the Tasmania (TAS) region is planned to be out of service from 1030 hrs on 26/04/2024 to 1500 hrs on 26/04/2024
A credible contingency event during this planned outage could cause a large reduction in generation in TAS.
Refer AEMO Network Outage Schedule (NOS) for further details.
Manager NEM Real Time Operations
[EventId:202404241735_review] Prices for interval 24-Apr-2024 17:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404241730_review] Prices for interval 24-Apr-2024 17:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404241725_review] Prices for interval 24-Apr-2024 17:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1720 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404241720_review] Prices for interval 24-Apr-2024 17:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1715 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404241715_review] Prices for interval 24-Apr-2024 17:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1710 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.