Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer AEMO Electricity Participant Notice 119595
The MINTARO MINTARO GAS direction is now expected to start at 0730 hrs 29/10/2024.
The direction update is issued at 2358 hrs 28/10/2024.
Manager NEM Real Time Operations
[EventId:202410281900_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 28 October 2024 19:00
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 28 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 28 October 2024.
Refer to market notice: 119600
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1900 hrs on 28 October 2024.
This is an AEMO autogenerated Market Notice.
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0030 hrs 30/10/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 28/10/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119569 is cancelled at 1800 hrs 28/10/2024
Manager NEM Real Time Operations
[EventId:202410281800_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 28 October 2024 18:00
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 28 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 28 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1800 hrs on 28 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410281620_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 28 October 2024 16:20
Issued by Australian Energy Market Operator Ltd at 1620 hrs on 28 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 28 October 2024.
Refer to market notice: 119587
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1620 hrs on 28 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410281600_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 28 October 2024 16:00
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 28 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 28 October 2024.
Refer to market notice: 119576
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1600 hrs on 28 October 2024.
This is an AEMO autogenerated Market Notice.
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/10/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119565 has been updated at 1550 hrs to the following:
[1.] From 1800 hrs 29/10/2024 to 1930 hrs 29/10/2024.
The forecast capacity reserve requirement is 1036 MW.
The minimum capacity reserve available is 721 MW.
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Cancellation time: 28/10/2024 15:39
Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Refer AEMO Electricity Market Notice 119561
Auto-generated on behalf of Manager NEM Real Time Operations