117008RESERVE NOTICE14/06/2024 03:44:04 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 21/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1800 hrs to 2100 hrs 21/06/2024.
The forecast capacity reserve requirement is 422 MW.
The minimum capacity reserve available is 419 MW.

AEMO Operations
117007RESERVE NOTICE14/06/2024 03:46:12 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 21/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116980 is cancelled at 1400 hrs 14/06/2024.

AEMO Operations
117006RESERVE NOTICE14/06/2024 03:41:42 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116978 has been updated at 1400 hrs 14/06/2024 to the following:

1.From 0000 hrs to 0100 hrs 19/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1477 MW.

2. From 0530 hrs to 0930 hrs 19/06/2024.
The forecast capacity reserve requirement is 1715 MW.
The minimum capacity reserve available is 1186 MW.

3. From 1530 hrs to 2359 hrs 19/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1156 MW.

AEMO Operations
116999RESERVE NOTICE14/06/2024 03:42:59 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116977 has been updated at 1400 hrs 14/06/2024 to the following:

1. From 0630 hrs to 0830 hrs 18/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1412 MW.

2. From 1630 hrs to 2359 hrs 18/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1376 MW.

AEMO Operations
116998PRICES SUBJECT TO REVIEW14/06/2024 02:35:16 PM

[EventId:202406141440_review] Prices for interval 14-Jun-2024 14:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1435 hrs on 14 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 14-Jun-2024 14:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116997RESERVE NOTICE14/06/2024 03:40:43 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116976 is cancelled at 1400 hrs 14/06/2024.

AEMO Operations
116995PRICES SUBJECT TO REVIEW14/06/2024 02:30:19 PM

[EventId:202406141435_review] Prices for interval 14-Jun-2024 14:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1430 hrs on 14 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 14-Jun-2024 14:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116994PRICES SUBJECT TO REVIEW14/06/2024 02:25:23 PM

[EventId:202406141430_review] Prices for interval 14-Jun-2024 14:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1425 hrs on 14 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 14-Jun-2024 14:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116993PRICES SUBJECT TO REVIEW14/06/2024 02:20:23 PM

[EventId:202406141425_review] Prices for interval 14-Jun-2024 14:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1420 hrs on 14 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 14-Jun-2024 14:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm