PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 24/09/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
From 1900 hrs 24/09/2024 to 2000 hrs 24/09/2024.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 311 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 24/09/2024
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118409 is cancelled at 2215 hrs 23/09/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 24/09/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
From 1900 hrs 24/09/2024 to 1930 hrs 24/09/2024.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 335 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118390 is cancelled at 07:15 hrs 23/09/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 2000 hrs 23/09/2024 to 2030 hrs 23/09/2024.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 308 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118387 is cancelled at 05:40 hrs 23/09/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 2000 hrs 23/09/2024 to 2030 hrs 23/09/2024.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 279 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118382 is cancelled at 22:40 hrs 22/09/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1930 hrs 23/09/2024 to 2000 hrs 23/09/2024.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 322 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations