Filter by category
Filter by Date
STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/10/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 118636 has been updated at 1000 hrs 07/10/2024 to the following:
[1.] From 1530 hrs to 1600 hrs 08/10/2024.
The forecast capacity reserve requirement is 774 MW.
The minimum capacity reserve available is 722 MW.
[2.] From 1700 hrs to 2000 hrs 08/10/2024.
The forecast capacity reserve requirement is 738 MW.
The minimum capacity reserve available is 280 MW.
AEMO is seeking a market response.
AEMO Operations.
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/10/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 118628 has been updated at 0700 hrs 07/10/2024 to the following:
From 1700 hrs to 2000 hrs 08/10/2024.
The forecast capacity reserve requirement is 710 MW.
The minimum capacity reserve available is 224 MW.
AEMO is seeking a market response.
AEMO Operations.
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/10/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period[s]:
[1.] From 1730 hrs 08/10/2024 to 2000 hrs 08/10/2024.
The forecast capacity reserve requirement is 846 MW.
The minimum capacity reserve available is 438 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/10/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 118625 is cancelled at 2230 hrs 05/10/2024.
No LOR2 condition is currently forecast in the STPASA period.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/10/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period[s]:
[1.] From 1730 hrs 08/10/2024 to 1800 hrs 08/10/2024.
The forecast capacity reserve requirement is 799 MW.
The minimum capacity reserve available is 767 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
CHG0098496 | Production | QLD Marketnet Router Replacement
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Market Network
Change Title: QLD Marketnet Router Replacement
Change Start Date & Time: 19/10/2024 14:00:53 AEST
Change End Date & Time: 19/10/2024 19:00:53 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage on the 19th October 2024:
IPWAN Participants - A brief interuption of up to 60 seconds while services are failover from QLD to NSW Datacenter.
Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10) only - All L2L connections should be established to both QLD / NSW.
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10) prior to this scheduled outage.
B2B VPN - No impact is expected.
SSL VPN Participants: None expected as SSL VPN's are hosted on a different device.
GASHUB: No impact is expected as GASHUB will be failed over to the NSW Datacenter.
Other Impacts will have been communicated in advance.
** FAILURE TO ENSURE VPN FAILOVER WILL RESULT IN LOSS OF MARKETNET CONNECTIVITY **
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0098133:NEM Reform - RMI (Retail Market Improvements) MSATS 54.0 - Completed
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Market Settlement & Transfer System
Change Title: NEM Reform - RMI (Retail Market Improvements) MSATS 54.0
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0098660:Telstra Melbourne Indial (03 9609 XXXX-XXXX)
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Cisco IP Phone
Change Title: Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0098666:Telstra Melbourne Indial (03 9609 XXXX-XXXX)
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Cisco IP Phone
Change Title: Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600