117564RESERVE NOTICE05/08/2024 09:25:40 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024

The actual LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117563 has been updated at 2120 hrs to the following:

The Actual LOR1 condition is forecast to exist until 2130 hrs.

The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 377 MW.

Manager NEM Real Time Operations
117563RESERVE NOTICE05/08/2024 08:44:48 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 2030 hrs.
The Actual LOR1 condition is forecast to exist until 2100 hrs.

The capacity reserve requirement is 450 MW
The minimum capacity reserve available is 428 MW

Manager NEM Real Time Operations
117546INTER-REGIONAL TRANSFER04/08/2024 10:56:12 AM

Inter-regional transfer limit variation - Keilor to Sth Morang 500kV Line - VIC region - 04/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Keilor to Sth Morang 500kV Line - VIC region - 04/08/2024

A planned outage of Keilor to Sth Morang 500kV Line in the VIC region was scheduled from 1000 hrs 04/08/2024 to 1300 hrs 04/08/2024.

The outage has been completed and Keilor to Sth Morang 500kV Line returned to service at 1050 hrs 04/08/2024

Constraint set(s) revoked: V-KTSM_R

Manager NEM Real Time Operations
117510RESERVE NOTICE30/07/2024 08:43:12 PM

Cancellation of Actual (LOR1) condition in the SA region - 30/07/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the SA region - 30/07/2024

The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No. 117509 is cancelled at 2040 hrs 30/07/2024.

Manager NEM Real Time Operations
117509RESERVE NOTICE30/07/2024 08:17:01 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 30/07/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 30/07/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 2000 hrs.
The Actual LOR1 condition is forecast to exist until 2030 hrs

The capacity reserve requirement is 450 MW
The minimum capacity reserve available is 404 MW

Manager NEM Real Time Operations
117508GENERAL NOTICE30/07/2024 02:45:25 PM

Increase to QNI limit to next hold point of 1400 MW Qld to NSW

AEMO ELECTRICITY MARKET NOTICE

Refer to market notices 117060.

AEMO, TransGrid, Powerlink have reviewed the test results following the QNI minor testing on 19th June 2024. The next hold point can now be released.

The hold point of 1400 MW from Qld to NSW will be implemented as of 1000 hrs 31st July 2024.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
117496INTER-REGIONAL TRANSFER28/07/2024 11:42:01 AM

Inter-regional transfer limit variation - Heywood - South East No 2 275 kV Line - SA region - 26/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -Heywood - South East No 2 275 kV Line SA region - 26/07/2024

A planned outage of Heywood - South East No 2 275 kV Line in the SA region was scheduled from 0830 hrs 26/07/2024 to 1730 hrs 28/07/2024.

The outage has been extended until 1200 hrs 29/07/2024

Constraint set(s) invoked:
I-HYSE
I-VS_050
I-VS+LKB_050

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
117466GENERAL NOTICE30/07/2024 09:20:28 PM

Network Augmentation Commissioned - VIC Region - 30/07/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - VIC Region - 30/07/2024

Cressy Terminal Station has been cut into the existing Moorabool - Mortlake No.2 500 kV line to form the following circuits:

Cressy - Mortlake No.2 500 kV line
Cressy - Moorabool No.2 500 kV line

Manager NEM Real Time Operations
117449INTER-REGIONAL TRANSFER25/07/2024 03:53:00 PM

Inter-regional transfer limit variation - Heywood M1 Transformer - VIC region - 25/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Heywood M1 Transformer - VIC region - 25/07/2024

A planned outage of Heywood M1 Transformer in the VIC region was scheduled from 0600 hrs 25/07/2024 to 1800 hrs 25/07/2024.

The outage has been completed and Heywood M1 Transformer returned to service at 1550 hrs 25/07/2024

Constraint set(s) revoked: V-HYTX_M12

Manager NEM Real Time Operations