Market Notices

119762RESERVE NOTICE02/11/2024 09:42:25 AM

STPASA - Update of the forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 119755 has been updated at 0940 hrs 02/11/2024 to the following:

[1.] From 1600 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 178 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
119757RESERVE NOTICE02/11/2024 09:36:36 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 04/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 119753 is cancelled at 0930 hrs 02/11/2024.

Manager NEM Real Time Operations
     
119755RESERVE NOTICE02/11/2024 08:00:37 AM

STPASA - Update of the forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 119751 has been updated at 0800 hrs 02/11/2024 to the following:

[1.] From 1800 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 470 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
119754RESERVE NOTICE02/11/2024 05:49:54 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 119752 has been updated at 0530 hrs 02/11/2024 to the following:

From 1800 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 535 MW.
The minimum capacity reserve available is 378 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
119753RESERVE NOTICE02/11/2024 05:51:08 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 04/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1800 hrs 04/11/2024 to 1830 hrs 04/11/2024.
The forecast capacity reserve requirement is 840 MW.
The minimum capacity reserve available is 829 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
119752RESERVE NOTICE01/11/2024 10:11:49 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 119737 has been updated at 2142 hrs 01/11/2024 to the following:

From 1730 hrs 07/11/2024 to 1930 hrs 07/11/2024.
The forecast capacity reserve requirement is 535 MW.
The minimum capacity reserve available is 149 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
119751RESERVE NOTICE01/11/2024 09:53:03 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 119750 has been updated at 2130 hrs 01/11/2024 to the following:

[1.] From 1630 hrs 07/11/2024 to 1930 hrs 07/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 140 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
119750RESERVE NOTICE01/11/2024 04:12:15 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 119738 has been updated at 1500 hrs 01/11/2024 to the following:

1. From 1800 hrs to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 400 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
119747RESERVE NOTICE01/11/2024 04:11:10 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119703 has been updated at 1400 hrs 01/11/2024 to the following:

1. From 1430 hrs to 1800 hrs 07/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 778 MW.

2. From 1900 hrs to 2000 hrs 07/11/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 832 MW.

AEMO Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm