Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 117214
The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 28/06/2024 will be inadequate to maintain a secure operating state in SA .
AEMO estimates that, in the absence of sufficient market response by 1600 hrs 27/06/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 03/07/2023
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117203 is cancelled at 1400 hrs 27/06/2024.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 02/07/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117202 is cancelled at 1400 hrs 27/06/2024.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 01/07/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117201 is cancelled at 1400 hrs 27/06/2024.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 117208
The synchronous generating units currently expected to be synchronised in SA from 1000 hrs 28/06/2024 will be inadequate to maintain a secure operating state in SA .
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA .
Manager NEM Real Time Operations
Possible intervention to manage power system security in SA Region
Possible intervention to manage power system security in SA Region
The synchronous generating units currently expected to be synchronised in SA from 0100 hrs 28/06/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 25/06/2024
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 25/06/2024
Refer Market Notice 117154
The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs 26/06/2024
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 03/07/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
1. From 0800 hrs to 0900 hrs 03/07/2024.
The forecast capacity reserve requirement is 532 MW.
The minimum capacity reserve available is 505 MW.
2. From 1730 hrs to 2030 hrs 03/07/2024.
The forecast capacity reserve requirement is 526 MW.
The minimum capacity reserve available is 496 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 02/07/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
1. From 0800 hrs to 0900 hrs 02/07/2024.
The forecast capacity reserve requirement is 536 MW.
The minimum capacity reserve available is 454 MW.
2. From 1730 hrs to 2130 hrs 02/07/2024.
The forecast capacity reserve requirement is 546 MW.
The minimum capacity reserve available is 414 MW.
AEMO Operations