Market Notices

117104MARKET INTERVENTION23/06/2024 07:53:31 AM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 22/06/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 22/06/2024

Refer Market Notice 117100

The AEMO Intervention Event and all associated directions are cancelled from 0750 hrs 23/06/2024

Manager NEM Real Time Operations
117101MARKET INTERVENTION22/06/2024 05:35:16 PM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 24/06/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
117100MARKET INTERVENTION22/06/2024 04:29:27 PM

Direction - SA region 22/06/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 22/06/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1635 hrs on 22/06/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
117098RESERVE NOTICE22/06/2024 02:29:27 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117094 has been updated at 1430 hrs 22/06/2024 to the following:

[1.] From 0630 hrs 24/06/2024 to 0930 hrs 24/06/2024.
The forecast capacity reserve requirement is 1703 MW.
The minimum capacity reserve available is 1430 MW.

[2.] From 1600 hrs 24/06/2024 to 2200 hrs 24/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1417 MW.

Manager NEM Real Time Operations
117097MARKET INTERVENTION22/06/2024 02:06:16 PM

Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE


Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 1000 hrs 23/06/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1630 hrs 22/06/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
117094RESERVE NOTICE21/06/2024 04:08:04 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

1. From 0700 hrs to 0830 hrs 24/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1705 MW.

2. From 1630 hrs to 1700 hrs 24/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1707 MW.

3. From 1730 hrs to 1930 hrs 24/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1702 MW.

AEMO Operations
117093GENERAL NOTICE21/06/2024 12:16:15 PM

Network Augmentation Commissioned - QLD Region - 21/06/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 21/06/2024

Commissioned:
H90 Tully South - T48 Tully 7162 132kV line
H90 Tully South No.1 275kV /132 kV transformer

Manager NEM Real Time Operations
117085RESERVE NOTICE20/06/2024 05:53:01 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.117084 is cancelled at 1745 hrs 20/06/2024.

Manager NEM Real Time Operations
117084RESERVE NOTICE20/06/2024 03:10:54 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.117080 has been updated at 1500 hrs to the following:

[1.] From 1730 hrs 20/06/2024 to 1900 hrs 20/06/2024.
The forecast capacity reserve requirement is 1770 MW.
The minimum capacity reserve available is 1682 MW.

Manager NEM Real Time Operations