Market Notices

112492MARKET INTERVENTION18/12/2023 04:27:44 PM

Direction - SA region 18/12/2023

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 18/12/2023

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1635 hrs on 18/12/2023.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
112489MARKET INTERVENTION18/12/2023 02:24:39 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 112482

The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 19/12/2023 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1630 hrs 18/12/2023, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
112488MARKET INTERVENTION18/12/2023 01:02:55 PM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 17/12/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 17/12/2023

Refer Market Notice 112469

The AEMO Intervention Event and all associated directions are cancelled from 1230 hrs 18/12/2023

Manager NEM Real Time Operations
112482MARKET INTERVENTION18/12/2023 05:05:06 AM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0100 hrs 19/12/2023 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
112470MARKET INTERVENTION17/12/2023 02:40:23 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 0100 hrs 18/12/2023 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 17/12/2023, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
112469MARKET INTERVENTION17/12/2023 05:02:10 PM

Direction - SA region 17/12/2023

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 17/12/2023

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1700 hrs on 17/12/2023.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
112467MARKET INTERVENTION17/12/2023 02:35:23 PM

Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 1700 hrs 18/12/2023 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 17/12/2023, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
112452MARKET INTERVENTION17/12/2023 05:05:07 PM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 16/12/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 16/12/2023

Refer Market Notice 112423

The AEMO Intervention Event and all associated directions are cancelled from 1700 hrs 17/12/2023

Manager NEM Real Time Operations
112449MARKET INTERVENTION17/12/2023 12:51:49 PM

Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in South Australia (SA) Region

The synchronous generating units currently expected to be synchronised in SA from 0100 hrs 18/12/2023 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm