Update - Non-credible contingency event - NSW region - 31/10/2024
Update - Non-credible contingency event - NSW region - 31/10/2024
Refer AEMO Electricity Market Notice 119689
At 0345 hrs the Wagga B 330 kV bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - NSW region - 31/10/2024
Non-credible contingency event - NSW region - 31/10/2024
At 0028 hrs the Wagga B 330 kV bus tripped which offloaded the Wagga - Walla Walla SF 6Y 330 kV line and Wagga No.3 transformer.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Update - Lightning vulnerable lines in Vic region
Update - Lightning vulnerable lines in Vic region
Refer to AEMO Electricity Market Notice 119029
At 1525 hrs on 18/10/2024 the Rowville - Yallourn No. 7 220 kV Line and the Rowville - Yallourn No. 8 220 kV Line tripped and auto-reclosed.
The cause of the trip was identified as due to Lightning.
In accordance with SO_OP_3715, AEMO now considers the Rowville - Yallourn No. 7 220 kV Line and the Rowville - Yallourn No. 8 220 kV Line to be vulnerable with a category of probable due to Lightning.
Manager NEM Real Time Operations
Update - Pre dispatch demand forecast - Qld region
Update - Pre dispatch demand forecast - Qld region
Refer market notice: 119666
The issue relating to the Queensland Pre dispatch demand forecast has been resolved.
Manager NEM Real Time Operations
Pre dispatch demand forecast - Qld region
Pre dispatch demand forecast - Qld region
AEMO is aware of an error in the Queensland pre dispatch demand forecast.
AEMO is currently working to resolve the issue.
Dispatch results are not impacted.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/10/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119607 is cancelled at 1230 hrs 29/10/2024
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/10/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119597 has been updated at 0745 hrs to the following:
[1.] From 1800 hrs 29/10/2024 to 1900 hrs 29/10/2024.
The forecast capacity reserve requirement is 1037 MW.
The minimum capacity reserve available is 947 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 28/10/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119569 is cancelled at 1800 hrs 28/10/2024
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/10/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119565 has been updated at 1550 hrs to the following:
[1.] From 1800 hrs 29/10/2024 to 1930 hrs 29/10/2024.
The forecast capacity reserve requirement is 1036 MW.
The minimum capacity reserve available is 721 MW.
Manager NEM Real Time Operations