Filter by category
Filter by Date
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120102
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 10/11/2024.
The direction update is issued at 1630 hrs 08/11/2024.
Manager NEM Real Time Operations
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer AEMO Electricity Participant Notice 120103
The MINTARO MINTARO GAS direction is now expected to commence at 2300 hrs 07/11/2024.
The direction update is issued at 1630 hrs 07/11/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 120077
Direction is cancelled from: 1730 hrs 07/11/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 120097
Direction is cancelled from: 1730 hrs 07/11/2024
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 06/11/2024
Cancellation - AEMO Intervention Event - SA region 06/11/2024
Refer to Market Notice 120012
The AEMO Intervention Event and all associated directions are cancelled from 1730 hrs on 07/11/2024.
Manager NEM Real Time Operations
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 120101
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 1600 hrs 07/11/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0130 hrs 08/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1700 hrs 08/11/2024
Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 120101
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1600 hrs 07/11/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 2300 hrs 07/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 09/11/2024
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region 07/11/2024
Direction - SA region 07/11/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 07/11/2024.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations