Market Notices

118029NON-CONFORMANCE01/09/2024 11:05:25 AM

NON-CONFORMANCE Region VIC1 Sunday, 1 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Sunday, 1 September 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MERCER01
Duration: 01/09/2024 11:00 to 01/09/2024 11:05
Amount: 122 MW
Constraint: NC-V_MERCER01

Auto-generated on behalf of Manager NEM Real Time Operations
118015NON-CONFORMANCE31/08/2024 03:25:22 PM

NON-CONFORMANCE Region SA1 Saturday, 31 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Saturday, 31 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: STARHLWF
Duration: 31/08/2024 14:50 to 31/08/2024 15:25
Amount: 26 MW
Constraint: NC-S_STARHLWF

Auto-generated on behalf of Manager NEM Real Time Operations
118014NON-CONFORMANCE31/08/2024 03:20:26 PM

NON-CONFORMANCE Region NSW1 Saturday, 31 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 31 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: HILLSTN1
Duration: 31/08/2024 15:05 to 31/08/2024 15:20
Amount: 85 MW
Constraint: NC-N_HILLSTN1

Auto-generated on behalf of Manager NEM Real Time Operations
118011NON-CONFORMANCE31/08/2024 01:55:23 PM

NON-CONFORMANCE Region SA1 Saturday, 31 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Saturday, 31 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MANNSF2
Duration: 31/08/2024 11:45 to 31/08/2024 13:55
Amount: 7 MW
Constraint: NC-S_MANNSF2

Auto-generated on behalf of Manager NEM Real Time Operations
117945NON-CONFORMANCE29/08/2024 03:40:16 PM

NON-CONFORMANCE Region QLD1 Thursday, 29 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 29 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GSTONE2
Duration: 29/08/2024 15:35 to 29/08/2024 15:40
Amount: 28 MW
Constraint: NC-Q_GSTONE2

Auto-generated on behalf of Manager NEM Real Time Operations
117923GENERAL NOTICE28/08/2024 12:46:15 PM

QNI Minor testing (NSW to Qld) 28th August 2024

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 117650

There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 850 MW on Wednesday 28th August 2024 from 1300 to 1700hrs.

This test includes a trip and reclose of a line in northern NSW.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
117904GENERAL NOTICE27/08/2024 05:00:48 PM

Network Augmentation Commissioned - VIC Region - 27/08/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - VIC Region - 27/08/2024

Cressy - Golden Plains No. 1 220 kV Line has been commissioned.
Golden Plains Terminal Station has been commissioned.

Manager NEM Real Time Operations
117772NON-CONFORMANCE24/08/2024 11:20:24 AM

NON-CONFORMANCE Region NSW1 Saturday, 24 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 24 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WYASF1
Duration: 24/08/2024 11:10 to 24/08/2024 11:20
Amount: 43 MW
Constraint: NC-N_WYASF1

Auto-generated on behalf of Manager NEM Real Time Operations
117760NON-CONFORMANCE23/08/2024 05:00:21 AM

NON-CONFORMANCE Region NSW1 Friday, 23 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 23 August 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: CAPBES1G, CAPBES1L
Aggregate Dispatch Group: CBESS_ADG1
Duration: 23/08/2024 04:35 to 23/08/2024 05:00
Amount: 13 MW
Constraint: NC-N_CBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm