Filter by category
Filter by Date
[EventId:202403151220_review] Prices for interval 15-Mar-2024 12:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1215 hrs on 15 March 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Mar-2024 12:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202403151215_review] Prices for interval 15-Mar-2024 12:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1210 hrs on 15 March 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Mar-2024 12:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202403151210_review] Prices for interval 15-Mar-2024 12:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1205 hrs on 15 March 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Mar-2024 12:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202403151205_review] Prices for interval 15-Mar-2024 12:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1200 hrs on 15 March 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Mar-2024 12:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Non-credible contingency event - SA region - 14/03/2024
Non-credible contingency event - SA region - 14/03/2024
At 2307 hrs the Tungkillo - Robertstown No. 1 275 kV Line and the Tungkillo East 275 kV Bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 12/03/2024
Non-credible contingency event - QLD region - 12/03/2024
At 0249 hrs the Strathmore - Clare South No 7208 132KV Line opened at Strathmore end only.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/03/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1930 hrs 11/03/2024 to 2030 hrs 11/03/2024.
The forecast capacity reserve requirement is 469 MW.
The minimum capacity reserve available is 402 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/03/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 115588 is cancelled at 0717 hrs 11/03/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/03/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 115587 has been updated at 0520 hrs to the following:
[1.] From 1930 hrs 11/03/2024 to 2000 hrs 11/03/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 545 MW.
Manager NEM Real Time Operations