115634PRICES SUBJECT TO REVIEW15/03/2024 12:15:19 PM

[EventId:202403151220_review] Prices for interval 15-Mar-2024 12:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1215 hrs on 15 March 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Mar-2024 12:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
115633PRICES SUBJECT TO REVIEW15/03/2024 12:10:23 PM

[EventId:202403151215_review] Prices for interval 15-Mar-2024 12:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1210 hrs on 15 March 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Mar-2024 12:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
115632PRICES SUBJECT TO REVIEW15/03/2024 12:05:17 PM

[EventId:202403151210_review] Prices for interval 15-Mar-2024 12:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1205 hrs on 15 March 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Mar-2024 12:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
115631PRICES SUBJECT TO REVIEW15/03/2024 12:00:23 PM

[EventId:202403151205_review] Prices for interval 15-Mar-2024 12:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1200 hrs on 15 March 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Mar-2024 12:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
115624POWER SYSTEM EVENTS14/03/2024 11:47:59 PM

Non-credible contingency event - SA region - 14/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - 14/03/2024

At 2307 hrs the Tungkillo - Robertstown No. 1 275 kV Line and the Tungkillo East 275 kV Bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
115595POWER SYSTEM EVENTS12/03/2024 03:29:42 AM

Non-credible contingency event - QLD region - 12/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 12/03/2024

At 0249 hrs the Strathmore - Clare South No 7208 132KV Line opened at Strathmore end only.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
115592RESERVE NOTICE11/03/2024 06:21:48 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/03/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 1930 hrs 11/03/2024 to 2030 hrs 11/03/2024.
The forecast capacity reserve requirement is 469 MW.
The minimum capacity reserve available is 402 MW.


Manager NEM Real Time Operations
115589RESERVE NOTICE11/03/2024 07:21:06 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/03/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 115588 is cancelled at 0717 hrs 11/03/2024.

Manager NEM Real Time Operations
115588RESERVE NOTICE11/03/2024 05:26:01 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/03/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 115587 has been updated at 0520 hrs to the following:

[1.] From 1930 hrs 11/03/2024 to 2000 hrs 11/03/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 545 MW.

Manager NEM Real Time Operations