[EventId:202312161150_confirmed] Prices for interval 16-Dec-2023 11:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1200 hrs on 16 December 2023
PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2023 11:50.
In accordance with Market Notice 112404 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202312161145_confirmed] Prices for interval 16-Dec-2023 11:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1200 hrs on 16 December 2023
PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2023 11:45.
In accordance with Market Notice 112403 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202312161140_confirmed] Prices for interval 16-Dec-2023 11:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1200 hrs on 16 December 2023
PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2023 11:40.
In accordance with Market Notice 112402 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
QNI Minor testing (NSW to Qld) 16th December 2023
Refer to market notice 110640
There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 750 MW on Tuesday 16th December from 0930 to 1800hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
Network Augmentation Commissioned - SA Region - 15/12/2023
Network Augmentation Commissioned - SA Region - 15/12/2023
Commissioned:
Bundey 330kV substation, 330kV East Bus and 330kV West Bus.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 14/12/2023
Cancellation of Actual (LOR1) condition in the NSW region - 14/12/2023
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.112357 is cancelled at 1940 hrs 14/12/2023.
Manager NEM Real Time Operations
Network Augmentation Commissioned - QLD Region - 14/12/2023
Network Augmentation Commissioned - QLD Region - 14/12/2023
Commissioned:
R15 MacIntyre 330 kV Switching Station
R14 Tummaville - R15 MacIntyre No.9918 330 kV Line
R14 Tummaville - R15 MacIntyre No.9919 330 kV Line
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/12/2023
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/12/2023
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1377 MW
The minimum capacity reserve available is 874 MW
Manager NEM Real Time Operations
[EventId:202312141555_confirmed] Prices for interval 14-Dec-2023 15:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1615 hrs on 14 December 2023
PRICES ARE NOW CONFIRMED for trading interval 14-Dec-2023 15:55.
In accordance with Market Notice 112339 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.