PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 14/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112263 has been updated at 2230 hrs to the following:
[1.] From 1630 hrs 14/12/2023 to 1830 hrs 14/12/2023.
The forecast capacity reserve requirement is 703 MW.
The minimum capacity reserve available is 337 MW.
AEMO is seeking a market response.
AEMO estimates the latest time at which it would need to intervene through an AEMO intervention event is 1500 hrs on 14/12/2023.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/12/2023
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 112257 has been updated at 2200 hrs to the following:
[1.] From 1730 hrs 14/12/2023 to 1800 hrs 14/12/2023.
The forecast capacity reserve requirement is 1284 MW.
The minimum capacity reserve available is 1076 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/12/2023
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112242 has been updated at 1830 hrs to the following:
[1.] From 1530 hrs 14/12/2023 to 1600 hrs 14/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1054 MW.
[2.] From 1900 hrs 14/12/2023 to 2000 hrs 14/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1160 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 14/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112241 has been updated at 1830 hrs to the following:
[1.] From 1600 hrs 14/12/2023 to 1900 hrs 14/12/2023.
The forecast capacity reserve requirement is 1000 MW.
The minimum capacity reserve available is 357 MW.
AEMO is seeking a market response.
AEMO estimates the latest time at which it would need to intervene through an AEMO intervention event is 1500 hrs on 14/12/2023.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/12/2023
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 112243 has been updated at 1630 hrs to the following:
From 1730 hrs 14/12/2023 to 1800 hrs 14/12/2023.
The forecast capacity reserve requirement is 1284 MW.
The minimum capacity reserve available is 1144 MW.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/12/2023
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1530 hrs to 1600 hrs 19/12/2023.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1315 MW.
AEMO Operations
CHG0082097 | Completed | Production | P3062 Manifestly Incorrect Inputs (MII)? Production Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: EMMS - Dispatch
Change Title: P3062 Manifestly Incorrect Inputs (MII) Production Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/12/2023
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1700 hrs 14/12/2023 to 1830 hrs 14/12/2023.
The forecast capacity reserve requirement is 1286 MW.
The minimum capacity reserve available is 988 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/12/2023
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1930 hrs 14/12/2023 to 2000 hrs 14/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1323 MW.