Non-credible contingency event - TAS region - 13/12/2023
Non-credible contingency event - TAS region - 13/12/2023
At 1324 hrs the Hadspen - Palmerston No.3 & No.4 110 kV lines tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
[EventId:202312131030_review] Prices for interval 13-Dec-2023 10:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1025 hrs on 13 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Dec-2023 10:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202312131025_review] Prices for interval 13-Dec-2023 10:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1020 hrs on 13 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Dec-2023 10:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202312131020_review] Prices for interval 13-Dec-2023 10:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1015 hrs on 13 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Dec-2023 10:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202312131015_review] Prices for interval 13-Dec-2023 10:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1010 hrs on 13 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Dec-2023 10:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202312131010_review] Prices for interval 13-Dec-2023 10:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1005 hrs on 13 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Dec-2023 10:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202312131005_review] Prices for interval 13-Dec-2023 10:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1000 hrs on 13 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Dec-2023 10:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
CHG0082097 | Production | P3062 Manifestly Incorrect Inputs (MII)? Production Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: P3062 Manifestly Incorrect Inputs (MII) Production Release
Change Start Date & Time: 12/12/2023 08:00:00 AEST
Change End Date & Time: 13/12/2023 17:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Under this change , AEMO will install an updated version of a key Dispatch application (NEMDE Solutionloader) used in Production for Dispatch, 5-Minute Pre-dispatch, Pre-dispatch, and 7-Day Pre-dispatch.
Changes include:
o Extension of Automated MII Procedures to include detection of FCAS MIIs using an FCAS requirement threshold.
No outages or delays expected. AEMO will advise once complete.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .