120106RESERVE NOTICE07/11/2024 03:51:05 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120094 has been updated at 1545 hrs to the following:

From 1730 hrs 07/11/2024 to 2000 hrs 07/11/2024.
The forecast capacity reserve requirement is 1075 MW.
The minimum capacity reserve available is 618 MW.

Manager NEM Real Time Operations
     
120105RESERVE NOTICE07/11/2024 03:48:33 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120104 has been updated at 1545 hrs to the following:

From 1730 hrs 07/11/2024 to 1930 hrs 07/11/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 991 MW.

Manager NEM Real Time Operations
     
120104RESERVE NOTICE07/11/2024 03:23:33 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

From1600hrs 07/11/2024 to 1700 hrs 07/11/2024
The forecast capacity reserve requirement is 1558 MW.
The minimum capacity reserve available is 1481 MW.

Manager NEM Real Time Operations
     
120096SETTLEMENTS RESIDUE07/11/2024 02:05:43 PM

[EventId:202411071405_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 07 November 2024 14:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1405 hrs on 7 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1405 hrs on 7 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
120095SETTLEMENTS RESIDUE07/11/2024 01:30:26 PM

[EventId:202411071330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 07 November 2024 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 7 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 November 2024.

Refer to market notice: 120076

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 7 November 2024.

This is an AEMO autogenerated Market Notice.
     
120094RESERVE NOTICE07/11/2024 01:19:34 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120052 has been updated at 1315 hrs to the following:

[1.] From 1730 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 1095 MW.
The minimum capacity reserve available is 934 MW.

Manager NEM Real Time Operations
     
120083RESERVE NOTICE07/11/2024 12:59:05 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

From 1730 hrs 08/11/2024 to 1900 hrs 08/11/2024.
The forecast capacity reserve requirement is 1120 MW.
The minimum capacity reserve available is 912 MW.

Manager NEM Real Time Operations
     
120080RESERVE NOTICE07/11/2024 12:54:47 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1800 hrs 08/11/2024 to 1900 hrs 08/11/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1348 MW.

Manager NEM Real Time Operations
     
120076SETTLEMENTS RESIDUE07/11/2024 12:04:04 PM

[EventId:202411071200_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 07 November 2024 12:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1200 hrs on 7 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1200 hrs on 7 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     