Filter by category
Filter by Date
[EventId:202410261405_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 26 October 2024 14:05
Issued by Australian Energy Market Operator Ltd at 1405 hrs on 26 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 26 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1405 hrs on 26 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation - MSL1- VIC Region at 1315 hrs 26/10/2024.
Cancellation - MSL1- VIC Region at 1315 hrs 26/10/2024.
Refer to Market Notice 119423 for MSL1.
Manager NEM Real Time Operations
[EventId:202410261100_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 26 October 2024 11:00
Issued by Australian Energy Market Operator Ltd at 1100 hrs on 26 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 26 October 2024.
Refer to market notice: 119425
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1100 hrs on 26 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410260915_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 26 October 2024 09:15
Issued by Australian Energy Market Operator Ltd at 0915 hrs on 26 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 26 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0915 hrs on 26 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Forecast Minimum System Load 1 (MSL1) in the VIC Region on 26/10/2024
Update to Market Notice 119236 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 26/10/2024.
Minimum regional demand is forecast to be 1302 MW at 1230 hrs, and the advisory threshold is:
MSL1 - 1685 MW
MSL2 - 1185 MW
MSL3 - 685 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1000 hrs to 1400 hrs 26/10/2024.
AEMO Operations
[EventId:202410251730_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 25 October 2024 17:30
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 25 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 25 October 2024.
Refer to market notice: 119417
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1730 hrs on 25 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410251615_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 25 October 2024 16:15
Issued by Australian Energy Market Operator Ltd at 1615 hrs on 25 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 25 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1615 hrs on 25 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410251445_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 25 October 2024 14:45
Issued by Australian Energy Market Operator Ltd at 1445 hrs on 25 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 25 October 2024.
Refer to market notice: 119408
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1445 hrs on 25 October 2024.
This is an AEMO autogenerated Market Notice.
Forecast Minimum System Load 1 (MSL1) in the VIC Region on 27/10/2024
Update to Market Notice 119315 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 27/10/2024.
Minimum regional demand is forecast to be 1732 MW at 1230 hrs, and the advisory threshold is:
MSL1 = 1795 MW
MSL2 = 1295 MW
MSL3 = 795 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1330 hrs 26/10/2024.
AEMO Operations