118665RESERVE NOTICE07/10/2024 11:08:07 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118664 has been updated at 2300 hrs to the following:

[1.] From 1730 hrs 08/10/2024 to 1900 hrs 08/10/2024.
The forecast capacity reserve requirement is 1198 MW.
The minimum capacity reserve available is 1045 MW.

Manager NEM Real Time Operations
     
118664RESERVE NOTICE07/10/2024 09:31:50 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118648 has been updated at 2130 hrs to the following:

[1.] From 1730 hrs 08/10/2024 to 1930 hrs 08/10/2024.
The forecast capacity reserve requirement is 1187 MW.
The minimum capacity reserve available is 863 MW.

Manager NEM Real Time Operations
     
118648RESERVE NOTICE07/10/2024 02:31:27 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118642 has been updated at 1430 hrs to the following:

[1.] From 1730 hrs 08/10/2024 to 1900 hrs 08/10/2024.
The forecast capacity reserve requirement is 1166 MW.
The minimum capacity reserve available is 1005 MW.

Manager NEM Real Time Operations
     
118642RESERVE NOTICE07/10/2024 01:15:46 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Periods:

[1.] From 1700 hrs 08/10/2024 to 1730 hrs 08/10/2024.
The forecast capacity reserve requirement is 1147 MW.
The minimum capacity reserve available is 904 MW.

[2.] From 1900 hrs 08/10/2024 to 2200 hrs 08/10/2024.
The forecast capacity reserve requirement is 1187 MW.
The minimum capacity reserve available is 731 MW.

Manager NEM Real Time Operations
     
118630RESERVE NOTICE06/10/2024 01:17:25 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118629 is cancelled at 1314 hrs 06/10/2024.

Manager NEM Real Time Operations
     
118629RESERVE NOTICE06/10/2024 12:56:44 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1730 hrs 07/10/2024 to 1930 hrs 07/10/2024.
The forecast capacity reserve requirement is 1108 MW.
The minimum capacity reserve available is 963 MW.

Manager NEM Real Time Operations
     
118596RESERVE NOTICE04/10/2024 02:52:16 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118562 has been updated at 1400 hrs 04/10/2024 to the following:

From 1730 hrs to 1930 hrs 08/10/2024.
The forecast capacity reserve requirement is 1097 MW.
The minimum capacity reserve available is 855 MW.

AEMO Operations
     
118562RESERVE NOTICE02/10/2024 03:38:42 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118548 has been updated at 1400 hrs 02/10/2024 to the following:

1. From 1730 hrs to 1930 hrs 08/10/2024.
The forecast capacity reserve requirement is 1107 MW.
The minimum capacity reserve available is 797 MW.

2. From 2100 hrs to 2130 hrs 08/10/2024.
The forecast capacity reserve requirement is 1118 MW.
The minimum capacity reserve available is 972 MW.

AEMO Operations
     
118548RESERVE NOTICE01/10/2024 03:10:01 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:

1. From 1730 hrs to 2030 hrs 08/10/2024.
The forecast capacity reserve requirement is 1108 MW.
The minimum capacity reserve available is 668 MW.

2. From 2100 hrs to 2200 hrs 08/10/2024.
The forecast capacity reserve requirement is 1120 MW.
The minimum capacity reserve available is 816 MW.