Market Notices

119267SETTLEMENTS RESIDUE23/10/2024 11:00:26 PM

[EventId:202410232300_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 23 October 2024 23:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2300 hrs on 23 October 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 October 2024.

Refer to market notice: 119266

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2300 hrs on 23 October 2024.

This is an AEMO autogenerated Market Notice.
     
119266SETTLEMENTS RESIDUE23/10/2024 10:05:20 PM

[EventId:202410232205_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 23 October 2024 22:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2205 hrs on 23 October 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 October 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 2205 hrs on 23 October 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
119265MARKET INTERVENTION23/10/2024 09:55:15 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119240

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1830 hrs 24/10/2024.

The direction update is issued at 2145 hrs 23/10/2024.

Manager NEM Real Time Operations
     
119264SETTLEMENTS RESIDUE23/10/2024 09:00:23 PM

[EventId:202410232100_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 23 October 2024 21:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2100 hrs on 23 October 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 October 2024.

Refer to market notice: 119262

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2100 hrs on 23 October 2024.

This is an AEMO autogenerated Market Notice.
     
119263RESERVE NOTICE23/10/2024 08:23:49 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119213 has been updated at 2000 hrs to the following:

[1.] From 1730 hrs 24/10/2024 to 1900 hrs 24/10/2024.
The forecast capacity reserve requirement is 1172 MW.
The minimum capacity reserve available is 910 MW.

Manager NEM Real Time Operations
     
119262SETTLEMENTS RESIDUE23/10/2024 08:05:29 PM

[EventId:202410232005_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 23 October 2024 20:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2005 hrs on 23 October 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 October 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 2005 hrs on 23 October 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
119261RECLASSIFY CONTINGENCY23/10/2024 07:44:11 PM

Cancellation of a Non-Credible Contingency Event: Gordon - Chapel St No 1 220kV line and Gordon - Chapel St No 2 220kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Gordon - Chapel St No 1 220kV and Gordon - Chapel St No 2 220kV

Cancellation time: 23/10/2024 19:44

Constraint set(s) revoked:
F-T-CSGO Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
T-CSGO_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 119258

Auto-generated on behalf of Manager NEM Real Time Operations
     
119260MARKET INTERVENTION23/10/2024 07:49:57 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119257

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 2000 hrs 23/10/2024.

The direction update is issued at 1945 hrs 23/10/2024.

Manager NEM Real Time Operations
     
119259SETTLEMENTS RESIDUE23/10/2024 07:30:28 PM

[EventId:202410231930_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 23 October 2024 19:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1930 hrs on 23 October 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 October 2024.

Refer to market notice: 119248

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1930 hrs on 23 October 2024.

This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm