Filter by category
Filter by Date
CHG0082504 | Pre-Production | Removal of support of TLS Version 1.1 and lower
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Market Network
Change Title: Removal of support of TLS Version 1.1 and lower
Change Start Date & Time: 14/02/2024 10:00:00 AEST
Change End Date & Time: 14/02/2024 14:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Pre-Production
Participant Impact and Requirements: Participants using TLS version 1.1 and lower, need to update their servers to use TLSv1.2 as a minimum. Failing to do so would impact the connectivity with AEMO. An outage is not expected but, there may be some minor interruptions during the change period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Direction - SA region 03/01/2024
Direction - SA region 03/01/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).
The direction was necessary to maintain the power system in a secure operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1005 hrs on 03/01/2024.
Intervention pricing does not apply to this AEMO intervention event.
Manager NEM Real Time Operations
Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 112984
The synchronous generating units currently expected to be synchronised in SA from 2100 hrs 03/01/2024 will be inadequate to maintain a secure operating state in SA .
AEMO estimates that, in the absence of sufficient market response by 1000 hrs 03/01/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 27/12/2023
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 27/12/2023
Refer Market Notice 112823
The AEMO Intervention Event and all associated directions are cancelled from 1700 hrs 02/01/2024
Manager NEM Real Time Operations
Possible intervention to manage power system security in SA Region
Possible intervention to manage power system security in SA Region
The synchronous generating units currently expected to be synchronised in SA from 2100 hrs 03/01/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Possible intervention to manage power system security in SA Region
Possible intervention to manage power system security in SA Region
The synchronous generating units currently expected to be synchronised in SA from 2200 hrs 02/01/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Update - Direction - SA Region - 27/12/2023
Update - Direction - SA Region - 27/12/2023
Refer Market Notice 112823
The AEMO intervention event that commenced from interval ending 1505 hrs on 27/12/2023 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Update - Direction - SA Region - 27/12/2023
Update - Direction - SA Region - 27/12/2023
Refer Market Notice 112823
The AEMO intervention event that commenced from interval ending 1505 hrs on 27/12/2023 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Update - Direction - SA Region - 27/12/2023
Update - Direction - SA Region - 27/12/2023
Refer Market Notice 112823
The AEMO intervention event that commenced from interval ending 1505 hrs on 27/12/2023 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations