Market Notices

119212PRICES SUBJECT TO REVIEW23/10/2024 12:45:23 PM

[EventId:202410231250_review] Prices for interval 23-Oct-2024 12:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1245 hrs on 23 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 23-Oct-2024 12:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
119211RESERVE NOTICE23/10/2024 01:03:39 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1800 hrs 24/10/2024 to 1930 hrs 24/10/2024.
The forecast capacity reserve requirement is 1420 MW.
The minimum capacity reserve available is 1306 MW.

Manager NEM Real Time Operations
     
119210PRICES SUBJECT TO REVIEW23/10/2024 12:40:29 PM

[EventId:202410231245_review] Prices for interval 23-Oct-2024 12:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1240 hrs on 23 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 23-Oct-2024 12:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
119209PRICES SUBJECT TO REVIEW23/10/2024 12:35:25 PM

[EventId:202410231240_review] Prices for interval 23-Oct-2024 12:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1235 hrs on 23 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 23-Oct-2024 12:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
119208NON-CONFORMANCE23/10/2024 12:25:15 PM

NON-CONFORMANCE Region SA1 Wednesday, 23 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Wednesday, 23 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: DALNTH1
Duration: 23/10/2024 12:15 to 23/10/2024 12:25
Amount: 14 MW
Constraint: NC-S_DALNTH1

Auto-generated on behalf of Manager NEM Real Time Operations
     
119207MARKET SYSTEMS23/10/2024 10:25:05 AM

CHG0099235 | Production | Migrate Pre-Production (PPD) VLAN 108 Gateway in Norwest from the Old Core Switches to the New Core Switches.


Change Number: CHG0099235
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Local Area Network
Change Title: Migrate Pre-Production (PPD) VLAN 108 Gateway in Norwest from the Old Core Switches to the New Core Switches.
Change Start Date & Time: 24/10/2024 10:00:00 AEST
Change End Date & Time: 24/10/2024 16:00:00 AEST
Outage Start Date & Time: 24/10/2024 11:57:00 AEST
Outage End Date & Time: 24/10/2024 12:02:00 AEST
Environment: Production
Participant Impact and Requirements:
Planned maintenance has been scheduled for the 24th October, commencing 11:57am - 12:02pm AEST. During this time there will be a brief outage (Up to 30 seconds) impacting the following Pre-Production systems:

- MSATS Retail
- EMMS Wholesale
- GAS Market Systems
- WA Market Systems

The maintenance being carried out relates to infrastructure only, no application or functional changes are being performed. If you experience system related issues beyond the outage window (12:02pm) please contact the AEMO Support Hub.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .






     
119206MARKET SYSTEMS23/10/2024 10:21:46 AM

CHG0099241 | Production | Migrate DEV / TEST / Pre-Production (PPD) VLAN 104 Gateway in Norwest from the Old Core Switches to the New Core Switches.

Change Number: CHG0099241
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Local Area Network
Change Title: Migrate DEV / TEST / Pre-Production (PPD) VLAN 104 Gateway in Norwest from the Old Core Switches to the New Core Switches.
Change Start Date & Time: 24/10/2024 10:00:00 AEST
Change End Date & Time: 24/10/2024 16:00:00 AEST
Outage Start Date & Time: 24/10/2024 11:57:00 AEST
Outage End Date & Time: 24/10/2024 12:02:00 AEST
Environment: Production
Participant Impact and Requirements:
Planned maintenance has been scheduled for the 24th October, commencing 11:57am - 12:02pm AEST. During this time there will be a brief outage (Up to 30 seconds) impacting the following Pre-Production systems:

- MSATS Retail
- EMMS Wholesale
- GAS Market Systems
- WA Market Systems

The maintenance being carried out relates to infrastructure only, no application or functional changes are being performed. If you experience system related issues beyond the outage window (12:02pm) please contact the AEMO Support Hub.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .




     
119205MARKET INTERVENTION23/10/2024 08:31:53 AM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119200

The updated required actions: Synchronise and follow dispatch targets at 0845 hrs 23/10/2024

The direction update is issued at 0830 hrs 23/10/2024.

Manager NEM Real Time Operations
     
119204SETTLEMENTS RESIDUE23/10/2024 08:15:25 AM

[EventId:202410230815_NRM_SA1_VIC1_stopped] NEGRES CONSTRAINT NRM_SA1_VIC1 ceased operating from 23 October 2024 08:15

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0815 hrs on 23 October 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 23 October 2024.

Refer to market notice: 119203

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the SA to VIC directional interconnector.

The negative residue constraint NRM_SA1_VIC1 ceased operating at 0815 hrs on 23 October 2024.

This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm