STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 19/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice 113337 is cancelled at 0430 hrs 17/01/2024.
No LOR2 condition is currently forecast in the STPASA period.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 19/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1500 hrs 19/01/2024 to 1600 hrs 19/01/2024.
The forecast capacity reserve requirement is 708 MW.
The minimum capacity reserve available is 671 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 18/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113285 is cancelled at 0700 hrs 16/01/2024.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
[EventId:202401160735_review] Prices for interval 16-Jan-2024 07:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 0730 hrs on 16 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jan-2024 07:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401160730_review] Prices for interval 16-Jan-2024 07:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 0725 hrs on 16 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jan-2024 07:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401160725_review] Prices for interval 16-Jan-2024 07:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 0720 hrs on 16 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jan-2024 07:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401160720_review] Prices for interval 16-Jan-2024 07:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 0715 hrs on 16 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jan-2024 07:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401160715_review] Prices for interval 16-Jan-2024 07:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 0710 hrs on 16 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jan-2024 07:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401160710_review] Prices for interval 16-Jan-2024 07:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 0705 hrs on 16 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jan-2024 07:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.