STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 14/12/2023
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1630 hrs 14/12/2023 to 1800 hrs 14/12/2023.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 655 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Non-credible contingency event - SA region - 11/12/2023
Non-credible contingency event - SA region - 11/12/2023
At 0444 hrs the Mintaro - Waterloo 132 kV Line tripped and the Clare North - Mintaro 132 kV Line tripped at the Mintaro end only.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
[EventId:202312091805_confirmed] Prices for interval 09-Dec-2023 18:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 9 December 2023
PRICES ARE NOW CONFIRMED for trading interval 09-Dec-2023 18:05.
In accordance with Market Notice 112141 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202312091825_confirmed] Prices for interval 09-Dec-2023 18:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 9 December 2023
PRICES ARE NOW CONFIRMED for trading interval 09-Dec-2023 18:25.
In accordance with Market Notice 112145 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202312091820_confirmed] Prices for interval 09-Dec-2023 18:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 9 December 2023
PRICES ARE NOW CONFIRMED for trading interval 09-Dec-2023 18:20.
In accordance with Market Notice 112144 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202312091815_confirmed] Prices for interval 09-Dec-2023 18:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 9 December 2023
PRICES ARE NOW CONFIRMED for trading interval 09-Dec-2023 18:15.
In accordance with Market Notice 112143 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202312091810_confirmed] Prices for interval 09-Dec-2023 18:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 9 December 2023
PRICES ARE NOW CONFIRMED for trading interval 09-Dec-2023 18:10.
In accordance with Market Notice 112142 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202312091800_confirmed] Prices for interval 09-Dec-2023 18:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 9 December 2023
PRICES ARE NOW CONFIRMED for trading interval 09-Dec-2023 18:00.
In accordance with Market Notice 112139 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112125 is cancelled at 0945 hrs 09/12/2023.
Manager NEM Real Time Operations