112185MARKET INTERVENTION11/12/2023 03:20:21 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 112176

The synchronous generating units currently expected to be synchronised in SA from 0900 hrs 12/12/2023 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 0800 hrs 12/12/2023, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
112178MARKET INTERVENTION11/12/2023 02:00:57 PM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 08/12/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 08/12/2023

Refer Market Notice 112159

The AEMO Intervention Event and all associated directions are cancelled from 1400 hrs 11/12/2023

Manager NEM Real Time Operations
112176MARKET INTERVENTION11/12/2023 12:46:58 PM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0700 hrs 12/12/2023 will be inadequate to maintain a secure operating state in SA.

AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
112168MARKET SYSTEMS11/12/2023 06:40:17 AM

CHG0081726 | Completed | Production | Renewal of webMethods ESB server certificate

Change Number: CHG0081726
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Business to Business data exchange
Change Title: Renewal of webMethods ESB server certificate
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
112167MARKET SYSTEMS11/12/2023 06:39:14 AM

CHG0082105 | Completed | Production | BAU Retail Maintenance Release

Change Number: CHG0082105
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management
Change Title: BAU Retail Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
112159MARKET INTERVENTION10/12/2023 05:05:58 PM

Update - Direction - SA Region - 08/12/2023

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 08/12/2023

Refer Market Notice 112113

The AEMO intervention event that commenced from interval ending 1635 hrs on 08/12/2023 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
112154RESERVE NOTICE09/12/2023 06:50:27 PM

Cancellation of Actual (LOR1) condition in the NSW region - 09/12/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 09/12/2023

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.112137 is cancelled at 1850 hrs 09/12/2023.

Manager NEM Real Time Operations
112138MARKET INTERVENTION09/12/2023 05:37:54 PM

Update - Direction - SA Region - 08/12/2023

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 08/12/2023

Refer Market Notice 112113

The AEMO intervention event that commenced from interval ending 1635 hrs on 08/12/2023 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
112137RESERVE NOTICE09/12/2023 05:16:02 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/12/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/12/2023

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.

The Actual LOR1 condition is forecast to exist until 1830 hrs.

The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1344 MW.