[EventId:202312131025_review] Prices for interval 13-Dec-2023 10:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1020 hrs on 13 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Dec-2023 10:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202312131020_review] Prices for interval 13-Dec-2023 10:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1015 hrs on 13 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Dec-2023 10:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202312131015_review] Prices for interval 13-Dec-2023 10:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1010 hrs on 13 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Dec-2023 10:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202312131010_review] Prices for interval 13-Dec-2023 10:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1005 hrs on 13 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Dec-2023 10:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202312131005_review] Prices for interval 13-Dec-2023 10:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1000 hrs on 13 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Dec-2023 10:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 14/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112216 has been updated at 0700 hrs 13/12/2023 to the following:
From 1500 hrs to 1900 hrs 14/12/2023.
The forecast capacity reserve requirement is 1239 MW.
The minimum capacity reserve available is 345 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 14/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112210 has been updated at 0500 hrs 13/12/2023 to the following:
rom 1530 hrs 14/12/2023 to 2000 hrs 14/12/2023.
The forecast capacity reserve requirement is 1111 MW.
The minimum capacity reserve available is 574 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 14/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112202 has been updated at 1500 hrs 12/12/2023 to the following:
From 1500 hrs to 1900 hrs 14/12/2023.
The forecast capacity reserve requirement is 1316 MW.
The minimum capacity reserve available is 474 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 14/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112198 has been updated at 1100 hrs 12/12/2023 to the following:
From 1500 hrs to 2000 hrs 14/12/2023.
The forecast capacity reserve requirement is 1426 MW.
The minimum capacity reserve available is 502 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.