Update Inter-Regional Transfer limit variation - Basslink 21/05/2024
Update Inter-Regional Transfer limit variation - Basslink
Refer AEMO Electricity Market Notice 116734
There was an unplanned outage of the Basslink interconnector at 0235 hrs. The Basslink interconnector has been returned to service.
The following constraint set was revoked at 0810 hrs 21/05/2024
I-BL_ZERO
The constraint set contains the following interconnector on the left hand side.
T-V-MNSP1
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Basslink 21/05/2024
Inter-Regional Transfer limit variation - Basslink
There has been an unplanned outage of the Basslink interconnector at 0235 hrs
The following constraint set was invoked at 0240 hrs 21/05/2024
I-BL_ZERO
The constraint set contains the following interconnector on the left hand side.
T-V-MNSP1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/05/2024
Inter-regional transfer limit variation - Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/05/2024
A planned outage of Tamworth - Armidale No. 86 330 kV Line in the NSW region was scheduled from 0800 hrs 07/05/2024 to 1800 hrs 20/05/2024.
The outage has been rescheduled to be completed by 1200 hrs 19/05/2024.
Constraint set(s) invoked:
N-ARTW_86
N-DM_SVC
N-TW_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - DAPTO - MARULAN 8 330KV Line- NSW region - 18/05/2024
Inter-regional transfer limit variation - DAPTO - MARULAN 8 330KV Line - NSW region - 18/05/2024
A planned outage of DAPTO - MARULAN 8 330KV Line in the NSW region was scheduled from 0830 hrs 27/04/2024 to 1200 hrs 20/05/2024.
The outage has been completed at 1750 hrs 18/05/2024.
Constraint set(s) revoked: N-DTMN_8_15M, N-X_3L+8
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,
NSW1-QLD1,
V-S-MNSP1
VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Update - Network Augmentation Commissioned - QLD Region - 15/05/2024
Update - Network Augmentation Commissioned - QLD Region - 15/04/2024
Refer Market notice: 115974 and 116446
Guybal Munjan 275 kV Switching Station has been commissioned.
The former Ross - Chalumbin No. 857 and Ross - Chalumbin No. 858 275 kV lines have been replaced with the following lines:
H13 Ross - H93 Guybal Munjan No. 8916 275 kV line
H13 Ross - H93 Guybal Munjan No. 8917 275 kV line
H93 Guybal Munjan - H32 Chalumbin No. 857 275 kV line
H93 Guybal Munjan - H32 Chalumbin No. 858 275 kV line
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Blyth West to Munno Para 275 kV line - SA region - 08/05/2024
Inter-regional transfer limit variation - Blyth West to Munno Para 275 kV line - SA region - 08/05/2024
At 1536 hrs 08/05/2024 there was an unplanned outage of Blyth West to Munno Para 275 kV line.
The following constraint set(s) invoked at 1545 hrs 08/05/2024
S-X_BGBW+BWMP
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Tamworth No. 1 330 kV Bus - NSW region - 08/05/2024
Inter-regional transfer limit variation - Tamworth No. 1 330 kV Bus - NSW region - 08/05/2024
A planned outage of Tamworth No. 1 330 kV Bus in the NSW region was scheduled from 1200 hrs 08/05/2024 to 1800 hrs 10/05/2024.
The outage has been cancelled at 1154 hrs 08/05/2024
Constraint set(s) revoked: N-TW_330_BUS1, N-LDTW_84
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1
N-Q-MNSP1
T-V-MNSP1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - DAPTO - MARULAN 8 330KV LINE - NSW region - 07/05/2024
Inter-regional transfer limit variation - DAPTO - MARULAN 8 330KV LINE - NSW region - 07/05/2024
A planned outage of DAPTO - MARULAN 8 330KV LINE in the NSW region was scheduled from 0830 hrs 27/04/2024 to 1000 hrs 07/05/2024.
The outage has been rescheduled to be completed by 1200 hrs 08/05/2024.
Constraint set(s) invoked: N-DTMN_8_15M
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Network Augmentation Commissioned - QLD Region - 02/05/2024
Network Augmentation Commissioned - QLD Region - 02/05/2024
Commissioned:
H13 Ross - H93 Guybal Munjan No.8917 275 kV line
Manager NEM Real Time Operations