Filter by category
Filter by Date
[EventId:202411021440_review] Prices for interval 02-Nov-2024 14:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1435 hrs on 2 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 02-Nov-2024 14:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer AEMO Electricity Participant Notice 119748
The MINTARO MINTARO GAS direction is now expected to end at 1700 hrs 03/11/2024.
The direction update is issued at 1600 hrs 02/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119745
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 04/11/2024.
The direction update is issued at 1600 hrs 02/11/2024.
Manager NEM Real Time Operations
[EventId:202411021430_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 02 November 2024 14:30
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 2 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 2 November 2024.
Refer to market notice: 119781
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1430 hrs on 2 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411021435_review] Prices for interval 02-Nov-2024 14:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 2 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 02-Nov-2024 14:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Reclassification of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE
Duration: 02/11/2024 14:27 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119744 has been updated at 1400 hrs 02/11/2024 to the following:
1. From 1700 hrs to 1730 hrs 07/11/2024.
The forecast capacity reserve requirement is 867 MW.
The minimum capacity reserve available is 840 MW.
2. From 1900 hrs to 1930 hrs 07/11/2024.
The forecast capacity reserve requirement is 978 MW.
The minimum capacity reserve available is 655 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 119754 has been updated at 1400 hrs 02/11/2024 to the following:
From 1730 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 535 MW.
The minimum capacity reserve available is 140 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 119762 has been updated at 1400 hrs 02/11/2024 to the following:
[1.] From 1530 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 142 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations