Market Notices

112221PRICES SUBJECT TO REVIEW13/12/2023 10:00:16 AM

[EventId:202312131005_review] Prices for interval 13-Dec-2023 10:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1000 hrs on 13 December 2023

PRICES ARE SUBJECT TO REVIEW for trading interval 13-Dec-2023 10:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
112199NON-CONFORMANCE12/12/2023 09:25:17 AM

NON-CONFORMANCE Region SA1 Tuesday, 12 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Tuesday, 12 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: NBHWF1
Duration: 12/12/2023 09:00 to 12/12/2023 09:25
Amount: 17 MW
Constraint: NC-S_NBHWF1

Auto-generated on behalf of Manager NEM Real Time Operations
112196MARKET SYSTEMS12/12/2023 07:05:08 AM

CHG0082097 | Production | P3062 Manifestly Incorrect Inputs (MII)? Production Release

Change Number: CHG0082097
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: P3062 Manifestly Incorrect Inputs (MII) Production Release
Change Start Date & Time: 12/12/2023 08:00:00 AEST
Change End Date & Time: 13/12/2023 17:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Under this change , AEMO will install an updated version of a key Dispatch application (NEMDE Solutionloader) used in Production for Dispatch, 5-Minute Pre-dispatch, Pre-dispatch, and 7-Day Pre-dispatch.

Changes include:
o Extension of Automated MII Procedures to include detection of FCAS MIIs using an FCAS requirement threshold.

No outages or delays expected. AEMO will advise once complete.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
112186MARKET SYSTEMS11/12/2023 03:54:11 PM

CHG0082301 | Production | Planned System Maintenance - Electricity MMS Production Bay transfer

Change Number: CHG0082301
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: Planned System Maintenance - Electricity MMS Production Bay transfer
Change Start Date & Time: 11/12/2023 13:00:00 AEST
Change End Date & Time: 13/12/2023 16:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The maintenance activity is not expected to have any impact. If any issues are identified because of this maintenance activity, please contact the AEMO Support Hub 1300 236 600 .
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
112173NON-CONFORMANCE11/12/2023 10:35:17 AM

NON-CONFORMANCE Region QLD1 Monday, 11 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 11 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GSTONE5
Duration: 11/12/2023 10:30 to 11/12/2023 10:35
Amount: 15 MW
Constraint: NC-Q_GSTONE5

Auto-generated on behalf of Manager NEM Real Time Operations
112168MARKET SYSTEMS11/12/2023 06:40:17 AM

CHG0081726 | Completed | Production | Renewal of webMethods ESB server certificate

Change Number: CHG0081726
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Business to Business data exchange
Change Title: Renewal of webMethods ESB server certificate
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
112167MARKET SYSTEMS11/12/2023 06:39:14 AM

CHG0082105 | Completed | Production | BAU Retail Maintenance Release

Change Number: CHG0082105
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management
Change Title: BAU Retail Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
112145PRICES SUBJECT TO REVIEW09/12/2023 06:20:29 PM

[EventId:202312091825_review] Prices for interval 09-Dec-2023 18:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1820 hrs on 9 December 2023

PRICES ARE SUBJECT TO REVIEW for trading interval 09-Dec-2023 18:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
112144PRICES SUBJECT TO REVIEW09/12/2023 06:15:29 PM

[EventId:202312091820_review] Prices for interval 09-Dec-2023 18:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1815 hrs on 9 December 2023

PRICES ARE SUBJECT TO REVIEW for trading interval 09-Dec-2023 18:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm