[EventId:202312131005_review] Prices for interval 13-Dec-2023 10:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1000 hrs on 13 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Dec-2023 10:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
STPASA - Update to the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/12/2023
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 112182 has been updated at 1400 hrs 12/12/2023 to the following:
From 1730 hrs to 1800 hrs 14/12/2023.
The forecast capacity reserve requirement is 1285 MW.
The minimum capacity reserve available is 1193 MW.
AEMO Operations
STPASA - Update to the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/12/2023
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112183 has been updated at 1400 hrs 12/12/2023 to the following:
From 2000 hrs to 2030 hrs 14/12/2023.
The forecast capacity reserve requirement is 1735 MW.
The minimum capacity reserve available is 1569 MW.
AEMO Operations
Request for Generator Recall Information for 14/12/2023 for QLD Region
Refer to AEMO Electricity Market Notice no. 112198. Additional generation in QLD could assist in alleviating the forecast LOR condition in NSW.
Please provide Generator Recall Information for the period 14/12/2023, by 1200 hrs on 13/12/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
Request for Generator Recall Information for 14/12/2023 for NSW Region
Refer to AEMO Electricity Market Notice no. 112198.
Please provide Generator Recall Information for the period 14/12/2023, by 1200 hrs on 13/12/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/12/2023
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112160 has been updated at 1400 hrs 11/12/2023 to the following:
From 1530 hrs to 2000 hrs 14/12/2023.
The forecast capacity reserve requirement is 1385 MW.
The minimum capacity reserve available is 700 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/12/2023
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1700 hrs to 2030 hrs 14/12/2023.
The forecast capacity reserve requirement is 1287 MW.
The minimum capacity reserve available is 1019 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/12/2023.
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112042 has been updated at 1530 hrs 10/12/2023 to the following:
From 1600 hrs 14/12/2023 to 1830 hrs 14/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1076 MW.
Manager NEM Real Time Operations
[EventId:202312091825_review] Prices for interval 09-Dec-2023 18:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 9 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 09-Dec-2023 18:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.