Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)
Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)
AEMO has been notified that the controls to vary Directlink output are unavailable until further notice.
Constraint set I-CTRL_ISSUE_TE invoked from 0025 hrs.
The constraint set contains equations with the following interconnector on the LHS:
N-Q-MNSP1
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112037 has been updated at 1300 hrs 07/12/2023 to the following:
From 1630 hrs 09/12/2023 to 1830 hrs 09/12/2023.
The forecast capacity reserve requirement is 1226 MW.
The minimum capacity reserve available is 960 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 08/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112038 is cancelled at 1000 hrs 07/12/2023.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 08/12/2023
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
From 1700 hrs to 1730 hrs 08/12/2023.
The forecast capacity reserve requirement is 1273 MW.
The minimum capacity reserve available is 1267 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112034 has been updated at 0900 hrs 07/12/2023 to the following:
From 1630 hrs to 1800 hrs 09/12/2023.
The forecast capacity reserve requirement is 1263 MW.
The minimum capacity reserve available is 1154 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112033 has been updated at 2025 hrs 06/12/2023 to the following:
[1.] From 1530 hrs 09/12/2023 to 1830 hrs 09/12/2023.
The forecast capacity reserve requirement is 1278 MW.
The minimum capacity reserve available is 816 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
[1.] From 1630 hrs 09/12/2023 to 1800 hrs 09/12/2023.
The forecast capacity reserve requirement is 1126 MW.
The minimum capacity reserve available is 893 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 08/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112019 is cancelled at 0525 hrs 05/12/2023.
No LOR2 condition is currently forecast in the STPASA period.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 08/12/2023
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1630 hrs 08/12/2023 to 1730 hrs 08/12/2023.
The forecast capacity reserve requirement is 1417 MW.
The minimum capacity reserve available is 1376 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations