Market Notices

115646SETTLEMENTS RESIDUE15/03/2024 02:10:29 PM

[EventId:202403151410_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 15 March 2024 14:10

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1410 hrs on 15 March 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 March 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1410 hrs on 15 March 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
115645SETTLEMENTS RESIDUE15/03/2024 02:00:18 PM

[EventId:202403151400_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 15 March 2024 14:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1400 hrs on 15 March 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 March 2024.

Refer to market notice: 115643

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1400 hrs on 15 March 2024.

This is an AEMO autogenerated Market Notice.
115643SETTLEMENTS RESIDUE15/03/2024 01:05:26 PM

[EventId:202403151305_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 15 March 2024 13:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1305 hrs on 15 March 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 March 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1305 hrs on 15 March 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
115630SETTLEMENTS RESIDUE15/03/2024 12:01:20 PM

[EventId:202403151200_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 15 March 2024 12:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1200 hrs on 15 March 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 March 2024.

Refer to market notice: 115629

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1200 hrs on 15 March 2024.

This is an AEMO autogenerated Market Notice.
115629SETTLEMENTS RESIDUE15/03/2024 10:05:15 AM

[EventId:202403151005_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 15 March 2024 10:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1005 hrs on 15 March 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 March 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1005 hrs on 15 March 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
115622MARKET INTERVENTION14/03/2024 04:10:11 PM

Update - Direction - SA Region - 13/03/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 13/03/2024

Refer Market Notice 115613

The AEMO intervention event that commenced from interval ending 1705 hrs on 13/03/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
115620MARKET INTERVENTION14/03/2024 01:00:34 PM

Cancellation - Possible intervention to manage power system security in South Australia (SA) region 14/03/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Possible intervention to manage power system security in South Australia (SA) region 14/03/2024

Refer Market Notice 115616

AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1300 hrs 14/03/2024.

Manager NEM Real Time Operations
115616MARKET INTERVENTION14/03/2024 06:11:06 AM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 2100 hrs 14/03/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
115613MARKET INTERVENTION13/03/2024 05:00:31 PM

Direction - SA region 13/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 13/03/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1705 hrs on 13/03/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm