Market Notices

113222MARKET INTERVENTION12/01/2024 01:31:48 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 113219

The synchronous generating units currently expected to be synchronised in SA from 0030 hrs 13/01/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 12/01/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
113220MARKET SYSTEMS12/01/2024 09:23:21 AM

INC0124489 | RESOLVED | Issue with PD-PASA runs

AEMO ELECTRICITY MARKET NOTICE
SERVICE INTERRUPTION - RESOLVED
Please be informed that we had issue with Pre-Dispatch Projected Assessment of System Adequacy (PDPASA) service which has been restored now.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
113219MARKET INTERVENTION12/01/2024 09:00:41 AM

Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in South Australia (SA) Region

The synchronous generating units currently expected to be synchronised in SA from 0030 hrs 13/01/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
113215MARKET INTERVENTION11/01/2024 05:15:38 PM

Update - Direction - SA Region - 10/01/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 10/01/2024

Refer Market Notice 113188

The AEMO intervention event that commenced from interval ending 1635 hrs on 10/01/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
113211MARKET INTERVENTION11/01/2024 02:30:24 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 113206

The synchronous generating units currently expected to be synchronised in SA from 0030 hrs 12/01/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 11/01/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
113206MARKET INTERVENTION11/01/2024 01:28:03 PM

Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in South Australia (SA) Region

The synchronous generating units currently expected to be synchronised in SA from 0730 hrs 12/01/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
113203MARKET SYSTEMS11/01/2024 11:33:50 AM

CHG0082517 | Production | Prod MSATS 50.0.4 LCCD Defect Release | CANCELLED

Change Number: CHG0082517
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Prod MSATS 50.0.4 LCCD Defect Release
Change Start Date & Time: 21/01/2024 10:00:00 AEST
Change End Date & Time: 21/01/2024 17:00:00 AEST
Outage Start Date & Time: 21/01/2024 10:00:00 AEST
Outage End Date & Time: 21/01/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
113188MARKET INTERVENTION10/01/2024 04:35:03 PM

Direction - SA region 10/01/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 10/01/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1635 hrs on 10/01/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
113185MARKET INTERVENTION10/01/2024 02:57:06 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 113178

The synchronous generating units currently expected to be synchronised in SA from 0001 hrs 11/01/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1630 hrs 10/01/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm